Punctuality development and delay explanation factors on Norwegian railways in the period 2005–2014

Punctuality development and delay explanation factors on Norwegian railways in the period 2005–2014 The paper revisits an investigation of delays and punctuality on Norwegian rail- roads from 2010, re-evaluating its findings and studying the effects of later measures put in place between 2010 and 2014. Norwegian railways saw a steady decline in punctuality from 2005–2010, prompting the establishment of a task force to under- stand the trends and patterns behind the delays on the network. Data was collected on punctuality and delays, as well as on factors that were likely causes of delays. The original study pointed to three main areas that cause delays during the period 2005–2009: (1) an increased error rate in infrastructure and rolling stock, (2) exten- sive work close to the tracks due to increased maintenance and renewals and (3) an inability to perform consistently even under normal weather conditions. Meas- ures were put in place to turn around the overall performance. Appending data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality changed as these measures have been put in place, some fac- tors remained influential: low temperature (< − 10 °C and < − 15 °C) and snowfall (> 10 cm), reduced train lengths and increased volume of train services (both freight and passenger trains) still contribute to delays and low punctuality. The paper con- tributes to the literature on empirical analyses of delay causes. However, it can also be read as an illustration of an approach for an ex post evaluation of effects from punctuality improvement initiatives. Keywords Punctuality analysis · Railway · Delays · Causes 1 Introduction This paper documents a revisit of an analysis of the punctuality of Norwegian rail- roads from 2010. In the expanded study, carried out 5  years after the initial inves- tigation, we looked into assumed causes of delays and low punctuality with the * Nils O. E. Olsson nils.olsson@ntnu.no Norwegian University of Science and Technology, 7491 Trondheim, Norway Vol.:(0123456789) 1 3 128 A. Økland, N. O. E. Olsson additional data from the period 2010–2014. The original study (Olsson et al. 2010) indicated that development in the delay hours in 2005–2009 was due to a combina- tion of three factors: (1) an increased error rate in infrastructure and rolling stock, (2) extensive work close to the tracks due to new investments and an increased amount of maintenance and (3) an inability to address normal variation of weather conditions. Following the initial investigation, several measures were put in place by several actors in the Norwegian Railway sector (infrastructure manager, passenger and freight train operators) in order to improve performance. Via correlation and regression analyses for the two periods, the article contributes to the scientific litera- ture on empirical analyses of delay causes by presenting a double investigation into causes of delays and low punctuality, as well as an approach for an ex post evalua- tion of effects from punctuality improvement initiatives. The revisit, enabled by new data on performance in the years following the analy- sis, provides a rare opportunity for re-evaluating the original findings. 1.1 Q uality indicators for railway performance: punctuality and delays Punctuality is an important element in the quality of service for both passenger and freight transport on railways. Several studies have shown that punctuality is of criti- cal significance to the customer satisfaction of railway travellers (Lam and Small 2001; Norheim and Ruud 2011); Salkonen and Paavilainen (2010). Punctuality is claimed to be one of the most important quality indicators in railroad operations (Nyström 2008; Seco and Gonçalves 2007). Several studies have concluded that punctuality is highly valued among railway customers (Andersson 2014; Coulombel and De Palma 2014; Kroes et  al. 2007; Palmqvist et  al. 2017; Paulley et  al. 2006; Rietveld et al. 2001; Wardman 2001). Li et al. (2010) found that travellers are willing to pay more for their fare in exchange for a reduction in travel time variability. Kroes et  al. (2007) highlight that in the greater Paris area, creating new infrastructure to develop the public transport network is of no use if the existing network is not of high quality. Hadiuzzaman et al. (2019) found that the perceived service quality for train travellers is related to both physical conditions and service of intercity trains. Monchambert and de Palma (2014) model the influence of punctuality on mode choice of commuters, illustrating that punctuality influences the choice between bus and train. According to van Hagen and Sauren (2014), NS (Nederlandse Spoorwe- gen) has developed a pyramid of customer preferences. The base of the pyramid is formed by the basic needs of reliability and safety. They describe punctuality (or reliability) as a “dissatisfier”, meaning that this quality aspect is rated negatively if it does not meet expectations. If the desire for punctuality is met, the passenger will experience a sense of control and be satisfied with the journey (but no more than that). Punctuality and delays are most often mentioned as similar terms but have differ - ent meanings. Delays are measured in time units, whereas punctuality is expressed through percentage. Parbo et al. (2016) say that punctuality, as a numerical measure- ment, is the percentage of trains arriving on time to the stations. To measure punctu- ality, one must define the threshold for when an arrival is counted as a delay. These 1 3 Punctuality development and delay explanation factors… 129 registration limits vary from country to country. For example, in Germany, the UK and the Netherlands, the delay limits are 5, 10 and 3 min, respectively (Hansen and Pachl 2008). In Japan, a train is considered delayed if it is more than 1 min behind schedule (Tomii, 2010). In Norway, a local train is on time if it reaches the destina- tion with less than 4 min (3 min and 59 s) delay, whereas a long-distance train is on time if it reaches the destination with less than 6 min (5 min and 59 s) delay. The 3 and 5  min limits used in Norway trace their origin to a time when punc- tuality was measured manually and in full minutes at the final destination of each train. Trains being more than 3 and 5 min delayed were considered as non-punctual. This was calculated as “>3” and “> 5” minutes and discussed as if the limits were 3 and 5 min, but these were actually in effect “≥ 4” and “≥ 6” minutes. To maintain consistency when delays came to be measured in seconds, the limits became 3 min and 59  s and 5  min and 59  s, respectively. Punctuality can be measured in several ways. The most common is based on arrival delay to the final destination (Parbo et  al. 2016), which is discussed above. Depending on data availability, which has been increasing in recent years (Wallander and Mäkitalo 2012), it is also possible to measure punctuality at any station (Palmqvist 2019). An alternative measure of delay is travel time variability (Noland and Polak 2002; Rietveld et  al. 2001), which is especially relevant for train traffic that is to a lesser extent based on timetables, such as some kinds of freight trains (Gorman 2009). While punctuality is typically measured based on the number of trains being delayed, Salkonen and Paavilainen (2010) call for a refocus of punctuality measures from the number of trains affected, to how (and how many) passengers are affected. This would mean to shift focus from train punctuality to traveller punctuality (Krist- offersson and Pyddoke 2019). While this may be a better measure of the railway sys- tem performance in terms of a user perspective, it is often a challenge to obtain data on passenger volumes (Sørensen et  al. 2018). An alternative approach is to study train interactions, and especially the share of interactions that occur as planned (Palmqvist and Tomii 2019). König (2020) provides a taxonomy scheme for railway punctuality problems and connects the field of delay management to other parts of the planning process. There are several approaches to research on punctuality, including optimization of timetables (Andersson et al. 2013) analysing historical traffic data (Benezech and Coulombel 2013; Takeuchi et  al. 2007) and studying timetable supplements (Vro- mans 2005). Another tradition is to study delay causes. This paper continues this lat- ter tradition. In the following, we give a brief overview of some research in the field. 1.2 P revious studies on causes of delays and low punctuality Harris and Godward (1992) listed five variables that affect the punctuality of trains and investigated their correlations to punctuality for three British datasets (InterCity, Network SouthEast and Regional) and one Dutch dataset. The study showed that two variables were statistically significant in determining punctuality, distance cov - ered from departure station and train length (in number of carriages). The other fac- tors investigated were: the previous number of station stops, age of a motive power 1 3 130 A. Økland, N. O. E. Olsson unit and track occupation. Ten years later, a similar study was performed on data from Norwegian railways by Olsson and Haugland (2004) and presented the correla- tion between delays and punctuality and the following factors: Number of travellers, Load factor (number of passengers/seats), Capacity utilization of tracks, Cancellations, Speed restrictions, Development close to tracks, Departure and arrival punctuality, Regulations for handling exceptions. The factors with the strongest correlation to punctuality were the number of trav- ellers, the load factor of the trains and departure punctuality. The impressions of practitioners had led to the authors expecting a stronger correlation than what was actually found between punctuality and capacity utilization and the reduction of speed. The weak degree of correlation seen in Olsson and Haugland (2004) led to new hypotheses regarding the relationship between the studied factors and punctual- ity. Rather than having a linear effect on punctuality, the various factors are expected to have threshold values. If thresholds are exceeded, punctuality is affected. Factors, such as capacity utilization and speed restrictions, can have such thresholds. If the thresholds are not exceeded, the effect of these factors is often hidden in the noise from other factors. Passenger behavior and numbers have been studied as an explanatory factor for delays (Heinz 2003; Palmqvist et al. 2020). Carey and Carville (2003) also highlight the importance of how train stations can influence punctuality. Harris et al. (2013) state that the time required for passenger boarding and alighting at stations is a criti- cal element of overall train service performance. Bender et al. (2013) studied how to manage an unknown number of passengers that want to board a train, the objective being to minimize the total delay of all passengers. Bergström and Krüger (2013) state that a major share of all delay time is associ- ated with the tail of the delay distribution. Thus, extreme delays cannot be neglected when prioritizing between measures designed to improve rail infrastructure. Berg- ström and Krüger (2013) also claim that delays are not only concentrated in size but are concentrated in space and time and follow a precise power law with respect to days and an exponential distribution with regard to stations. In terms of punctuality, their study showed that large and small delays had an equal influence on the overall punctuality (assuming a small delay is more than the delay threshold of 4 min). Several European studies have looked into the effects of severe weather condi- tions as a potential explanation for delays. Xia et  al. (2013) studied how weather conditions affect train operator and railway infrastructure performance in the Nether - lands. Their study documented that wind gusts, snow, precipitation, temperature and leaves had strong positive effects on the number of infrastructure disruptions, and a strong effect on train arrival punctuality and cancellation rates. Several weather- related aspects, such as snow, leaves, high temperatures and variation in temperature 1 3 Punctuality development and delay explanation factors… 131 within the day, have negative impacts on punctuality and cancellation rates. Their impacts are, in general, indirect by causing disturbances in the railway infrastruc- ture. Gusts, precipitation and low temperatures, on the other hand, have both direct and indirect effects. Ludvigsen and Klæboe (2014) presented four cases of how the harsh 2010 winter weather affected rail freight operations in Norway, Sweden, Swit- zerland and Poland. The study emphasized the reactive behavior of rail managers who mobilized to reduce the adverse outcomes. During the snowy and cold winter of 2009/2010, many problems occurred. Eleven countries experienced rolling stock problems (Enno Wiebe 2010). According to Szafránski (2011) and Trafikverket (2010), problems that occurred in Sweden were related to four different areas: infra- structure, contractor capacity, internal management and process, and public relations with passengers and operators. More recently, Wang and Zhang (2019) found that severe weather was strongly influencing train delays. Railway capacity has been widely assumed to be an important factor regarding train punctuality, especially concerning the volume of secondary delays. Gibson et al. (2002) undertook an extensive study on the relationship between capacity utili- zation and delays in the UK. Their aim was to find empirical justification for conges- tion charges on the parts of the railway network with the highest capacity utilization. Wenyi et  al. (2010) studied delays on Chinese high-speed railways, with a special focus on delays caused by the train control system; they found the train control sys- tem accounted for 10% of total delays of 5 min or more. The availability of large amounts of data from railway systems has resulted in more analyses of punctuality and delays, laying the foundations for enhanced timeta- bling, simulations, driver assistance and train dispatching. Examples include Huang et al. (2011) and Zhou and Mi (2013), who analysed the effect of speed restrictions based on simulations. Liu et al. (2009) discuss optimal driving patterns on lines with speed restrictions. In summary, in the railway literature there is a large tradition of simulation-based approaches for timetable and punctuality analyses. We have briefly reviewed empiri- cal studies that investigate factors that influence punctuality. Common factors that are analysed in such studies include weather, availability of infrastructure and roll- ing stock, capacity utilization, passenger behavior and train dispatching. 1.3 Notes on special characteristics of Norwegian railways The Norwegian railway network consists of railway tracks that extend to 4087  km across the country from North to South. There are 2622  km of electrified tracks, 242 km of double-tracks, 60 km of high-speed tracks, 696 tunnels and 2760 bridges (Jernbaneverket 2015). Two special features of the network are the relatively low share of double-tracks and high share of non-electrified railway (38% is not elec- trified). The major tracks for long-distance, regional and freight trains are single- tracked. Nearly all double-tracks are located in the larger Oslo-area, where there is a continuous construction of new double-tracked lines. The Oslo area is important for the rail traffic for two reasons: the majority of trains (with the majority of travellers) 1 3 132 A. Økland, N. O. E. Olsson run there, and train traffic in the Oslo area affects the trains in large parts of the country. Two different measurements related to delays are used in Norway. One is related to delays to the final destination and is a measurement of time or percentage of trains that are considered as delayed. The other measure is related to registered delay causes. When trains are more than 4 min delayed or additionally delayed, train dis- patchers are required to register a delay cause. Delays are registered while under way, and a train number can get several registrations of additional delays. These delays are summarized and referred to as delay hours. A train may hence accumu- late delay hours even though it arrives punctually at the final destination. The delay hours are allocated to operators, infrastructure or traffic management. 1.4 Development in overall punctuality: 2005–2010 The number of delay hours allocated to passenger trains was largely on a steady rise from 2005 to 2010. There was an increase in most categories for the period as a whole. For the operators on the Drammen–Eidsvoll route (mainly NSB and the Airport express train), the number of delay hours remained stable until the win- ter of 2009–2010. The winters of 2007 and 2009 also showed an increase in delay hours, but the variation in delay hours during the year remained remarkably stable. The winter of 2009–2010 stands out as having a higher peak in the number of delay hours and that it took longer for the number of monthly delay hours to return to nor- mal levels. For the infrastructure manager, the situation with regards to delay hours gradu- ally deteriorated over the period from 2005 to 2010. In addition to an increase in the average number of delay hours from year to year, the variation from week to week also increased significantly.  The winter of 2009–2010 was a continuation of the trend regarding the number of delay hours for the infrastructure manager. 1.5 Measur es taken from 2010 Several efforts were put in place to improve the reliability of the rail system from 2010. Some measures were relatively straightforward: extra capacity (manpower) for removal of snow at strategically important parts of the infrastructure (especially switches), and electric heating of switches was gradually put in place. Conductor rails were installed in the Oslo tunnel to reduce the tearing down of the overhead power line. New rolling stock was put in place (introduced from December 2012) to serve local and regional traffic in the greater Oslo region. Additionally, a new timetable for the greater Oslo area was put in place in December 2013 as well. Publicity campaigns in the form of posters at the stations and on the platforms were produced to change traveller behavior regarding how to board and alight from the train, as described by Harris, Mjøen and Haugland. Markings were made on the platforms to facilitate positioning for the travellers preparing to board the train, as 1 3 Punctuality development and delay explanation factors… 133 well as making it easier for the train drivers to stop at an appropriate place at the platform. Finally, the funds dedicated to operations and maintenance for the Infrastructure Manager has increased year-by-year throughout the period (as well as the funds for infrastructure investment). 1.6 Development in overall punctuality: 2010–2014 The years 2009 and 2010 stand out as years of crisis for Norwegian railways. In what has been regarded as an “annus horribilis”, many of the things that could go wrong did go wrong. The cold winter and the large number of delays ensured an increased focus on robustness in case similar conditions were to occur again. Fig- ure 1 shows the delay hours on Norwegian railways in the period from 2005 to the end of 2014. The years following 2010 have a similar volume of delays as the years prior to 2010. 2 Methods 2.1 The task force and its mandate Following an initiative from the Ministry of Transportation, a task force consisting of representatives from the infrastructure manager (IM), three train operating com- panies (TOCs) for people transport, and the largest goods operator was established to review the development in punctuality and delay hours over the period from 2005 to the winter of 2009/2010. In the year 2005, registration of punctuality and delay hours-registration was automated (although the tagging of delay-codes remained a manual task). Therefore, 2005 was a natural starting point for the review. The intro- duction of automated registration coincided with the highest average punctuality level registered for the Norwegian railways. A team of two researchers was engaged to organize and facilitate four workshops with the task force and to conduct analyses between each session using data pro- vided by the participants. The analyses laid the groundwork for the task force’s work on identifying the causes for delays and causes to reduce the amount of yearly delay hours and to increase punctuality. The following was defined as a mandate for the work: “Reviewing developments in delay hours and identify the underlying root cause(s) as for why the trend shows a steadily deteriorating development from 2005 until now (2010). This includes inves- tigating potential connections with changes in operating conditions and traffic vol- ume. Recognized statistical methods are to be used. Special in-depth analyses can be performed on identified problem areas or the implementation of measurements in areas where data are not available.” The participating TOCs and the IM willingly shared their data, under the pre- requisite that sensitive data should remain with the researchers and that all analyses would be presented to the task force (a list of the data used is included in Sect. 2.2). 1 3 134 A. Økland, N. O. E. Olsson 1 3 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Fig. 1 Delay-hours per month and three-month moving average for the Norwegian railways (sum of delays for goods and passenger trains) from 2005–2014. Values are indexed. 100 equals average number of delay hours per month for 2000 Punctuality development and delay explanation factors… 135 The willingness to share information based on sensitive data was grounded in the understanding of a secondary, unofficial goal of the task force: Creating a shared understanding of the current status and performance of the rail system and thus cooling down an ongoing public “blame game” in the media. Analyses were con- ducted between sessions, and preliminary findings were sent to the participants for review before each meeting. Potential root causes, referred to as “assumed causes of delays and low punctuality” in the following, along with questions regarding the analyses were discussed in the group. The original task force analysis covered the period from 2005 to the first months of 2010. When we remade the analyses including the development from 2010 and onwards, we wanted to have data sets that were as comparable as possible. The analyses therefore cover two periods of five full years, January 2005 to Decem- ber 2009, and January 2010 to December 2014, in addition to analyses of the full 10-year period. Examining data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality has changed as various measures have been put in place, some factors remain influential: Low temperature (< −  10  °C and < −  15  °C) and snowfall (> 10  cm), reduced train lengths and increased vol- ume of train services (freight and passenger trains) still contribute to delays and low punctuality. The relationship between Infrastructure Management activity (opera- tions, maintenance and investment) appears to have been reversed in the second period. The overall punctuality has improved since 2010; however, the performance of the record year 2005 has not been duplicated. This paper is a continuation of the work done in the task force. We study punc- tuality-influencing factors in the period 2005 to 2009, as well as the same factors in the second period from 2010 to 2014. The paper utilizes a wider dataset and a longer time period compared to the initial study by Zakeri and Olsson (2017). 2.2 Data sources Data that captured factors which were expected to influence punctuality and delays internally and externally to the actors were collected with a resolution of per day, per week and per month. Throughout this article, the emphasis will rest on the results and the analyses of the aggregated “per month” dataset, covering the com- plete network. 2.2.1 Dependent variables: punctuality and delays Measures of punctuality and delay hours collected from 2005 to the end of 2014 were treated as dependent variables in the regression analyses. The data used for the analyses are specified in Table  1, including the dependent variables representing punctuality and delays used in the study. Punctuality was measured as the percent of trains arriving less than 4 min (local trains) or 6 min (freight and long-distance pas- senger trains) to their final destination. Delay hours were based on registered delays 1 3 136 A. Økland, N. O. E. Olsson 1 3 Table 1 Overview of dependent variables, punctuality and delay hours Punctuality aspect Indicator name Description of Indicator Unit Data source Punctuality Local passenger (NSB) Monthly punctuality for local passenger Percent trains arriving on time at final Arrival time registrations trains destination Regional passenger (NSB) Monthly punctuality for regional pas- Percent trains arriving on time at final Arrival time registrations senger trains destination Long distance passenger (NSB) Monthly punctuality for long distance pas- Percent trains arriving on time at final Arrival time registrations senger trains destination Airport express train Monthly punctuality for Airport express Percent trains arriving on time at Garder- Arrival time registrations trains moen airport Freight Monthly punctuality for freight trains Percent trains arriving on time at final Arrival time registrations destination Delay hours Infrastructure manager Delay hours registered on infrastructure Number of delay hours Delay cause registrations related delay cause codes All operators Delay hours registered on operator-related Number of delay hours Delay cause registrations delay cause codes NSB Delay hours registered as caused by NSB Number of delay hours Delay cause registrations Airport express Delay hours registered as caused by Air- Number of delay hours Delay cause registrations port express trains Freight Delay hours registered as caused by freight Number of delay hours Delay cause registrations trains Punctuality development and delay explanation factors… 137 at any point along a train route. If a train gets an increase in delay by 4 min or more between two measuring points, the cause for the delay increase is registered by the train dispatchers. The delay hour measure is the sum of these registered delays for a given line in a given time period. Punctuality and delay hours were chosen as variables because they are well estab- lished in the Norwegian railway industry. Traffic quality was measured based on these variables, and the indicators were discussed at regular quality evaluation meet- ings between the infrastructure manager and the operators. The variables, however, have some weaknesses. For example, the number of passengers is not represented in the measures. 2.2.2 Independent variables: causes of delay and low punctuality The independent variables consisted of measures of Infrastructure Manager activity (operations, maintenance and investment), volume of transport services for freight and passenger services (ton and ton-kilometers for freight operators and train and seat kilometer produced by passenger train operators) and the number of passengers. Additional independent variables related to passenger transport included changes to the type of rolling stock used for passenger trains, especially reduced seat capacity. Measures of performance at the freight terminals included departure delays from the main terminal. Factors related to weather and climate were included in the analy- ses. Weather was hypothesized to negatively influence delays and punctuality when snowfall, precipitation and low temperature hit certain thresholds. Registrations from three measuring posts in and around Oslo were collected and used in the analy- ses (Blindern, Asker and Gardermoen, respectively). The thresholds used were the number of days with – 10 °C and – 15 °C, the number of days with equal or more than 10 mm precipitation and the number of days with snowfall of 10 cm or more for each measuring post. These thresholds were defined in co-operation with the taskforce industry participants. An index was constructed for each factor combining the number of days each factor had exceeded the thresholds at each station. Table 2 is a summary of independent variables and how they are measured. The factors that were assumed to influence punctuality are a less well-established group of variables. The choice of variables was based on literature studies and previ- ous research but also based on data availability. As independent researchers, we had access to data that in general is considered to be company-internal information to the train operators. This was the case for data about passenger rolling stock avail- ability, and measures from freight terminals. Data on weather and infrastructure spending were added because both aspects were highlighted by industry representa- tives in the task force. 2.2.3 Modelling delays and punctuality Regression models of delays and punctuality on the network were developed iteratively as data were made available. The first step in the analyses consisted of calculating the correlation coefficient of the independent variables and the meas- ures of punctuality and delay hours. Correlation does not mean causation, so the 1 3 138 A. Økland, N. O. E. Olsson 1 3 Table 2 Overview of independent variables, potential drivers of delays and low punctuality Influencing factor Indicator name Description of Indicator Unit Data source Weather Days below – 10 °C Days below – 10 °C during one Number of days Weather data month Days below – 15 °C Days below – 15 °C during one Number of days Weather data month Days snowfall > 10 cm Days snowfall > 10 cm during one Number of days Weather data month Days precipitation > 10 mm Number of days precipita- Number of days Weather data tion > 10 mm during one month Infrastructure manager activity Funds for operations Yearly funds for railway infrastruc- NOK Governmental budget ture operations allocated to IM Funds for maintenance Yearly funds for maintenance rail- NOK Governmental budget way operations allocated to IM Funds for operations and mainte- Sum of yearly funds for railway NOK Governmental budget nance infrastructure operations and maintenance allocated to IM Funds for investments Yearly funds for Investments rail- NOK Governmental budget way investments allocated to IM Passenger transport Seat km tot Passenger seat-km produced by Number of km Train operators NSB in total, for the whole country Seat km Oslo Passenger seat-km produced by Number of km Train operators NSB in Oslo area Train km tot Train-km produced by NSB in Number of km Train operators total, for the whole country Train km Oslo Train-km produced by NSB in Number of km Train operators Oslo area Punctuality development and delay explanation factors… 139 1 3 Table 2 (continued) Influencing factor Indicator name Description of Indicator Unit Data source Rolling stock passenger trains Reduced seat capacity Number of departures planned Number of trains Train operator internal registrations with double or triple EMUs which are run with one EMU less than planned Rolling stock faults Number of registered rolling stock Number of trains Train operator internal registrations faults Change of rolling stock type Number of departures run with Number of trains Train operator internal registrations other type of rolling stock than planned Cancellations NSB Cancellations of NSB trains per Number of cancellations Punctuality statistics month Departure delay main terminal Departure delay main terminal Number of cancellations Freight operator internal registra- Freight operation tions Freight train ready for departure Freight train ready for departure, Minutes Freight operator internal registra- average delay tions Freight rolling stock ready from Freight rolling stock ready from Minutes Freight operator internal registra- maintenance maintenance, average delay tions Numbers from NSB AS, the former main national train operator 140 A. Økland, N. O. E. Olsson expertise of the task force was put to the test with identifying causes of delays and low punctuality. The correlation within the set of independent variables was subsequently cal- culated to investigate if the variables were internally independent. The correlation between punctuality and delay hours was calculated. In addition, one-way analyses of variance (one-way ANOVA) were carried out to further investigate the relation- ship between the weather and delay hours and punctuality. The discussions based on simple correlation factors form the basis for the regres- sion analyses and the ordinary least square models of the railway system. Three models were developed for each of the independent variables: a complete model that used the complete data set of independent variables, a model consisting of only sta- tistically significant variables in which independent variables were removed step- by-step based on their p value, and a reduced model in which only the assumed primary explanatory factors are included. The coefficients have been calculated for 2005–2009, 2010–2014 and 2005–2014. Standardized coefficients have been calcu- lated for the reduced models. The availability of relevant data combined with detailed knowledge from the participants in the task force facilitated the identification process of connections between incidents, general (known) issues and delays. The analyses are based on a data set including the assumed delay causes and potential explanatory factors, from different databases belonging to the participants (including punctuality data and maintenance records for infrastructure and rolling stock), in addition to other avail- able data sources (most importantly data on weather). The punctuality and delay data have been studied in relation to a number of possible explanatory variables to uncover correlations and causes. All of the data requested by the task force were made available. Preliminary results were presented and reviewed by the task force for quality assurance. 3 Analysis of punctuality and influencing factors 3.1 Factors influencing punctuality To begin with, we show an analysis of correlations between the different depend- ent variables and between the independent ones. Table  3 presents correlation coef- ficients (Pearson product-moment correlation coefficient or Pearson’s r) for the cor - relation between delay hours (sum and delay hours allocated to the actor responsible for the delays) and punctuality (both overall and broken down into various types of traffic). These factors are treated as dependent variables in the subsequent analyses. There is a high degree of correlation between delay hours allocated to the various actors and punctuality for different types of traffic. The correlation between delay hours and punctuality is also high, indicating that although it is possible for trains to generate delay hours while still being on time at the final destination (and hence being punctual according to the statistic), these variables are not independent of each other. 1 3 Punctuality development and delay explanation factors… 141 1 3 Table 3 Pearson product-moment correlation coefficients (Pearson’s r) of current quality measures for the railway system, Delay hours and punctuality (dependent vari- ables) Delay hours Punctuality Dispatching Infra- Sum All operators All passenger Airport Long-distance Inter-City Local trains Freight trains structure trains express passenger passenger (Oslo) manager train trains trains Delay hours  Dispatching 0.63 0.80 0.80 − 0.81 − 0.73 − 0.47 − 0.61 − 0.68 − 0.67  Infrastructure 0.63 0.84 0.57 − 0.68 − 0.61 − 0.76 − 0.80 − 0.74 − 0.60 manager  Sum 0.80 0.84 0.88 − 0.74 − 0.77 − 0.68 − 0.76 − 0.75 − 0.71  All operators 0.80 0.57 0.88 − 0.77 − 0.79 − 0.49 − 0.56 − 0.56 − 0.67 Punctuality  All passenger − 0.81 − 0.68 − 0.74 − 0.77 0.81 0.64 0.73 0.69 0.71 trains  Airport express − 0.73 − 0.61 − 0.77 − 0.79 0.81 0.48 0.64 0.60 0.62 train  Long-distance − 0.47 − 0.76 − 0.68 − 0.49 0.64 0.48 0.71 0.63 0.57 passenger trains  Inter-City pas- − 0.61 − 0.80 − 0.76 − 0.56 0.73 0.64 0.71 0.86 0.65 senger trains  Local trains − 0.68 − 0.74 − 0.75 − 0.56 0.69 0.60 0.63 0.86 0.69 (Oslo)  Freight trains − 0.67 − 0.60 − 0.71 − 0.67 0.71 0.62 0.57 0.65 0.69 Coefficients not significant at the 0.05 level are in regular font 142 A. Økland, N. O. E. Olsson 1 3 Table 4 Pearson product-moment correlation coefficients (Pearson’s r) between assumed causes of delays and low punctuality Budget Budget Budget Invest- Seat Train Seat Train Pas- Pas- Freight Freight Depar- Delay Precip- − 10 °C − 15 °C Snow- km km senger senger tonnage ton– ture ready itation fall opera- mainte- O&M ment km km tions nance total total east east volume volume kilom- delay termi- AET eters termi- nal nal Budget 1.00 0.82 0.96 0.92 0.55 0.58 − 0.90 0.52 0.86 0.88 0.73 − 0.88 0.12 0.24 0.07 0.02 0.03 − 0.24 opera- tions Budget 0.82 1.00 0.95 0.72 0.42 0.42 − 0.84 0.42 0.58 0.82 0.35 − 0.84 0.16 0.25 0.03 0.14 0.19 − 0.23 mainte- nance Budget 0.96 0.95 1.00 0.86 0.51 0.52 − 0.92 0.49 0.75 0.89 0.57 − 0.91 0.15 0.26 0.05 0.09 0.12 − 0.25 O&M Invest- 0.92 0.72 0.86 1.00 0.66 0.62 − 0.75 0.56 0.95 0.86 0.80 − 0.75 0.01 0.04 0.05 − 0.02 0.00 − 0.24 ment Seat kilo- 0.55 0.42 0.51 0.66 1.00 0.89 − 0.37 0.86 0.70 0.65 0.59 − 0.39 − 0.02 − 0.16 0.01 0.06 0.04 − 0.13 meters total Train 0.58 0.42 0.52 0.62 0.89 1.00 − 0.45 0.96 0.65 0.55 0.60 − 0.49 − 0.03 − 0.08 − 0.06 0.10 0.06 − 0.11 kilo- meters total Seat kilo- − 0.90 − 0.84 − 0.92 − 0.75 − 0.37 − 0.45 1.00 − 0.36 − 0.67 − 0.75 − 0.60 0.98 − 0.13 − 0.28 0.00 − 0.11 − 0.15 0.27 meters east Train 0.52 0.42 0.49 0.56 0.86 0.96 − 0.36 1.00 0.58 0.53 0.49 − 0.40 − 0.01 − 0.07 − 0.08 0.11 0.06 − 0.05 kilo- meters east Passenger 0.86 0.58 0.75 0.95 0.70 0.65 − 0.67 0.58 1.00 0.83 0.90 − 0.67 − 0.01 − 0.06 0.03 − 0.04 − 0.04 − 0.21 volume Passenger 0.88 0.82 0.89 0.86 0.65 0.55 − 0.75 0.53 0.83 1.00 0.63 − 0.71 0.11 0.13 0.07 0.03 0.04 − 0.22 volume AET Punctuality development and delay explanation factors… 143 1 3 Table 4 (continued) Budget Budget Budget Invest- Seat Train Seat Train Pas- Pas- Freight Freight Depar- Delay Precip- − 10 °C − 15 °C Snow- opera- mainte- O&M ment km km km km senger senger tonnage ton– ture ready itation fall tions nance total total east east volume volume kilom- delay termi- AET eters termi- nal nal Freight 0.73 0.35 0.57 0.80 0.59 0.60 − 0.60 0.49 0.90 0.63 1.00 − 0.57 − 0.06 − 0.13 − 0.01 − 0.07 − 0.07 − 0.24 tonnage Freight − 0.88 − 0.84 − 0.91 − 0.75 − 0.39 − 0.49 0.98 − 0.40 − 0.67 − 0.71 − 0.57 1.00 − 0.12 − 0.26 0.04 − 0.12 − 0.17 0.25 ton-kil- ometers Departure 0.12 0.16 0.15 0.01 − 0.02 − 0.03 − 0.13 − 0.01 − 0.01 0.11 − 0.06 − 0.12 1.00 0.67 0.02 0.01 0.04 0.01 delay termi- nal Delay 0.24 0.25 0.26 0.04 − 0.16 − 0.08 − 0.28 − 0.07 − 0.06 0.13 − 0.13 − 0.26 0.67 1.00 0.09 − 0.07 − 0.03 − 0.06 ready termi- nal Precipita- 0.07 0.03 0.05 0.05 0.01 − 0.06 0.00 − 0.08 0.03 0.07 − 0.01 0.04 0.02 0.09 1.00 − 0.39 − 0.31 − 0.16 tion − 10 °C 0.02 0.14 0.09 − 0.02 0.06 0.10 − 0.11 0.11 − 0.04 0.03 − 0.07 − 0.12 0.01 − 0.07 − 0.39 1.00 0.87 0.39 − 15 °C 0.03 0.19 0.12 0.00 0.04 0.06 − 0.15 0.06 − 0.04 0.04 − 0.07 − 0.17 0.04 − 0.03 − 0.31 0.87 1.00 0.18 Snowfall − 0.24 − 0.23 − 0.25 − 0.24 − 0.13 − 0.11 0.27 − 0.05 − 0.21 − 0.22 − 0.24 0.25 0.01 − 0.06 − 0.16 0.39 0.18 1.00 Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in italic font. Coefficients not significant at the 0.05 level are in regular font 144 A. Økland, N. O. E. Olsson Table  4 presents the correlation between the assumed causes of delays and low punctuality. The assumed causes are treated as independent variables in the subse- quent analyses. However, several of them are not independent of each other. The funds available for operations, maintenance and investment appear to be coupled so that the increase in funding throughout 2010–2014 has resulted in an even increase for each activity. The increased funding has also had a capacity-increasing effect on the network, indicated by a strong correlation between funds and freight ton-kilome- tres and passenger volumes. Weather, constituted by precipitation, snowfall and low temperatures, appears to be independent of all the other assumed causes of low punctuality and delays in the analyses. The same is the case for performance at the freight terminal, as captured by the variables “delay at terminal” and “ready at terminal”. 3.2 C orrelation between assumed causes of delays and low punctuality and the performance of the railway system The following tables present correlation coefficients (Pearson product-moment cor - relation coefficient or Pearson’s r) for the correlation between assumed explanation factors (or drivers of delays and low punctuality) and the performance of the railway system, as expressed by punctuality and/or delay hours. We present the correlation coefficients for the periods 2005–2009 (before the initial study), 2010–2014 (the period after the study as several actions were put in place) and the combined period of 2005–2014 in Tables 5 and 6. Correlation coef- ficients that are significant at the 0.01 level are marked with bold font, those signifi- cant at the 0.05 level are in italic font in the tables. Although not all changes between the periods can be attributed to actions taken from 2010, special note should be taken of factors assumed to be causes of delays and low punctuality of which the direction of the relationship changes (from − to +) or becomes (in-)significant. Table  5 presents the correlation coefficients between delay hours and assumed causes of delays and low punctuality. For the initial period under investigation, there are significant correlations between factors considered to be the responsibility of all the actors (infrastructure manager, passenger and freight operators) and the sum of delays on the railways. Increased infrastructure manager activity, increased number of passengers and increases in freight all coincide with increases in delays. In addi- tion, low temperatures coincided with periods with increased numbers of delays. For the second period (2010–2014), many of these relationships changed or appeared to be dissolved. Infrastructure manager activity increased as delays were reduced, the relationship between the number of train and seat kilometres and delays became insignificant and the number of passengers increased as delays were reduced. The relationship between freight volumes and delays appear to have been reversed or dissolved. The relationship between weather and delays, however, correlates to a higher degree in the second period. The analyses of variance (ANOVA) between weather and punctuality are largely in line with the findings based on correlation. Low temperatures appear to influence overall delay hours and delay hours attributed to the train operating companies in both periods. There is a statistically significant 1 3 Punctuality development and delay explanation factors… 145 1 3 Table 5 Pearson product-moment correlation coefficients (Pearson’s r) between delays and assumed drivers of causes and low punctuality Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Weather Precipitation 0.19 − 0.23 − 0.07 0.28 − 0.05 0.09 0.05 − 0.29 − 0.16 0.19 − 0.18 − 0.03 (> 10 mm) Temperature 0.39 0.62 0.54 0.16 0.19 0.2 0.58 0.77 0.71 0.32 0.46 0.4 (< − 10) Temperature 0.43 0.64 0.57 0.27 0.24 0.26 0.56 0.75 0.68 0.3 0.51 0.42 (< − 15) Snowfall 0.25 0.33 0.1 0.04 0.09 − 0.03 0.38 0.41 0.28 0.34 0.18 0.25 (> 10 cm) IM activ- Funds for 0.68 − 0.47 0.3 0.69 − 0.26 0.29 0.57 − 0.55 − 0.01 0.55 − 0.46 − 0.1 ity operations Funds for 0.68 0.45 0.58 0.71 0.17 0.51 0.56 0.48 0.31 0.51 0.53 0.2 mainte- nance Sum of 0.71 − 0.28 0.46 0.73 − 0.2 0.41 0.59 − 0.36 0.16 0.55 − 0.23 0.05 funds for O&M Investments 0.67 − 0.35 0.22 0.71 − 0.17 0.25 0.54 − 0.46 − 0.08 0.56 − 0.32 − 0.1 146 A. Økland, N. O. E. Olsson 1 3 Table 5 (continued) Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Passenger Seat km total 0.48 − 0.06 0.27 0.43 − 0.01 0.27 0.38 − 0.12 0.08 0.56 0.04 0.19 trans- Seat km 0.27 − 0.06 − 0.38 0.14 − 0.01 − 0.28 0.26 − 0.12 − 0.08 0.43 0.04 0.07 port Oslo Train km 0.14 − 0.09 0.19 0.05 − 0.09 0.13 0.11 − 0.1 0.03 0.35 0.02 0.11 total Train km 0.23 − 0.09 0.21 0.11 − 0.09 0.14 0.22 − 0.1 0.08 0.42 0.02 0.17 Oslo Number of 0.7 − 0.42 0.11 0.72 − 0.16 0.2 0.55 − 0.52 − 0.18 0.65 − 0.41 − 0.18 passengers Number of 0.69 − 0.48 0.41 0.7 − 0.22 0.44 0.55 − 0.57 0.12 0.65 − 0.49 0.09 airport express train trav- ellers Rolling Reduced seat 0.53 0.57 0.49 0.48 0.5 0.44 0.54 0.52 0.52 0.34 0.49 0.44 stock capacity pas- senger trains Punctuality development and delay explanation factors… 147 1 3 Table 5 (continued) Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Freight Tons trans- − 0.21 − 0.45 − 0.04 − 0.19 − 0.17 0.05 − 0.22 − 0.54 − 0.3 − 0.09 − 0.48 − 0.3 opera- ported tion Tons–kilom- 0.41 − 0.27 − 0.36 0.33 − 0.24 − 0.26 0.36 − 0.16 − 0.06 0.51 − 0.4 0.08 eter freight Freight 0.56 0.06 0.19 0.33 0.06 0.15 0.71 0 0.08 0.45 0.13 0.13 rolling ready from terminal Departure 0.63 0.15 0.25 0.55 0.15 0.23 0.61 0.11 0.18 0.55 0.1 0.16 delay terminal Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in italic font. Coefficients not significant at the 0.05 level are in regular font 148 A. Økland, N. O. E. Olsson 1 3 Table 6 Pearson product-moment correlation coefficients (Pearson’s r) between punctuality and assumed causes of delays and low punctuality Influencing Punctuality passenger trains Punctuality regional traffic Punctuality IC Punctuality local traffic Punctuality freight factor 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Weather  Precipitation − 0.18 0.19 0.03 − 0.16 0.16 0.03 − 0.18 − 0.01 − 0.07 − 0.19 − 0.02 − 0.07 − 0.11 0.17 0.05 (> 10 mm)  Temperature − 0.42 − 0.49 − 0.43 − 0.24 − 0.20 − 0.23 − 0.35 − 0.20 − 0.27 − 0.40 − 0.20 − 0.27 − 0.47 − 0.33 − 0.38 (< − 10)  Temperature − 0.45 − 0.56 − 0.45 − 0.23 − 0.26 − 0.27 − 0.46 − 0.30 − 0.34 − 0.43 − 0.30 − 0.34 − 0.38 − 0.30 − 0.31 (< − 15)  Snowfall − 0.34 − 0.24 − 0.30 − 0.13 − 0.11 − 0.02 − 0.26 − 0.10 − 0.09 − 0.36 0.01 − 0.09 − 0.43 − 0.17 − 0.26 (> 10 cm) Infrastructue manager activity  Funds for − 0.45 0.57 0.23 − 0.38 0.27 − 0.22 − 0.52 0.42 − 0.22 − 0.43 0.35 − 0.16 − 0.24 0.55 − 0.03 operations  Funds main- − 0.39 − 0.43 − 0.06 − 0.39 0.00 − 0.35 − 0.48 − 0.25 − 0.43 − 0.33 − 0.27 − 0.34 − 0.14 − 0.36 − 0.23 tenance  Sum of funds − 0.43 0.41 0.09 − 0.41 0.31 − 0.30 − 0.51 0.33 − 0.34 − 0.38 0.24 − 0.26 − 0.18 0.42 − 0.14 O&M  Investments − 0.42 0.46 0.25 − 0.47 0.28 − 0.14 − 0.45 0.37 − 0.12 − 0.34 0.24 − 0.11 − 0.17 0.38 0.02 Passenger transport  Seat km Oslo 0.04 0.24 0.20 0.26 0.28 0.09 0.03 0.33 0.03 − 0.17 0.24 − 0.03 0.02 0.10 − 0.02  Train km − 0.06 0.20 − 0.14 0.11 0.25 0.28 − 0.01 0.27 0.30 − 0.23 0.12 0.24 − 0.05 − 0.01 0.16 total  Train km 0.00 0.24 0.17 0.21 0.28 0.10 0.01 0.33 0.02 − 0.21 0.24 − 0.06 − 0.03 0.10 − 0.04 Oslo  Number of − 0.52 0.49 0.29 − 0.53 0.21 − 0.13 − 0.49 0.37 − 0.06 − 0.45 0.25 − 0.06 − 0.28 0.37 0.05 passengers  Number of − 0.53 0.56 0.04 − 0.56 0.25 − 0.34 − 0.45 0.42 − 0.29 − 0.47 0.34 − 0.24 − 0.33 0.47 − 0.14 passengers AET Punctuality development and delay explanation factors… 149 1 3 Table 6 (continued) Influencing Punctuality passenger trains Punctuality regional traffic Punctuality IC Punctuality local traffic Punctuality freight factor 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Rolling stock passenger trains  Reduced seat − 0.48 − 0.64 − 0.58 − 0.44 − 0.58 − 0.49 − 0.54 − 0.56 − 0.51 − 0.36 − 0.53 − 0.45 − 0.25 − 0.36 − 0.30 capacity Freight operation  Tons trans- 0.05 0.50 0.36 0.08 0.19 − 0.04 0.07 0.38 0.03 0.02 0.30 0.03 − 0.06 0.38 0.08 ported  Ton kilom- − 0.34 0.23 − 0.17 − 0.30 0.10 0.24 − 0.22 0.14 0.28 − 0.44 0.42 0.24 − 0.42 0.39 0.12 eter freight  Departure − 0.58 − 0.05 − 0.11 − 0.47 − 0.14 − 0.21 − 0.60 0.02 − 0.11 − 0.52 − 0.05 − 0.14 − 0.49 − 0.10 − 0.17 delay terminal Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in regular font. Coefficients not significant at the 0.05 level are marked with a strikethrough line Year-by-year allocations from the National Budget Numbers from NSB AS, the former national train operator (now Vy) 150 A. Økland, N. O. E. Olsson relationship between snowfall and delay hours attributed to dispatching for both periods. Delay hours attributed to the infrastructure manager follow a similar pattern. Spe- cial note should be taken of the strong degree of correlation between infrastructure manager activities in the period 2005–2009. In the subsequent period of 2010–2014, the correlation is no longer significant. Delay hours attributed to the Infrastructure Manager in the second period appear to be largely independent of all the assumed causes of delays and low punctuality, the only exceptions being reduced train length (which is a factor under the train operators’ control) and funds for operations (which correlates negatively with IM delay hours in the second period, hence increased funding indicates a reduced number of delay hours). Delay hours attributed to the passenger train operating companies correlate closer with weather in the second period than in the initial period. Production volume (seat and train kilometres) and the number of passengers correlate less closely in the sec- ond period, where the correlation is largely insignificant. The correlation between incidents of reduced train length and delay hours attributed to passenger train opera- tors remain approximately unchanged from the initial to the second period. Similarly, delay hours attributed to dispatching correlate more closely with the weather in the second period compared to the initial period. Production volume (seat and train kilometres) and the number of travellers correlate closely with delay hours attributed to dispatching in the initial period. In the second period, the relation- ship appears to be insignificant. As was the case with delay hours attributed to the infrastructure manager and the passenger train operators, incidents of reduced train length correlate with delay hours in the second period. The relationship between freight train volumes and performance at the terminals is reversed or dissolved in the second period. Table  6 presents the Pearson correlation factors between assumed causes of delays and low punctuality and punctuality of different types of train traffic. The causes of low punctuality are expected to contribute to a lowering in the percentage of trains that reach their destination on time, so the correlation coefficients are nega- tive when the relationship is as expected. The correlation coefficients of the assumed causes of low punctuality and punc- tuality are for most of the cases in the region of −  0.4 for the 2005–2009 period. The exceptions are production volumes (seat and passenger train kilometers and tons transported) and precipitation, all of which are close to zero and not significant. The correlation between bad weather and low punctuality is lower for the sec- ond period for local passenger traffic and freight. For overall punctuality and bad weather, the correlation coefficients are higher in the second period with strong snowfall as the only exception. The correlation between assumed causes of delays and low punctuality and over- all punctuality changes very little between the two periods in the investigation. Punc- tuality for regional traffic, on the other hand, oversees a reduction in factors with a significant correlation from eight in the initial period to a single significant variable in the second period. The reduction in variables that correlates at the 0.01-level with punctuality for local traffic is similarly reduced from 12 in the initial period to one in 1 3 Punctuality development and delay explanation factors… 151 the second period (three variables have correlation coefficients that are significant at the 0.01-level in both periods, but the signs have changed). There were several instances of reversed relationships between the assumed causes of low punctuality and punctuality for freight trains from the initial to the second period in the investigation. 3.3 Regression models of delays and punctuality Following the pairwise correlations, we present the regression models in which the identified factors’ relationship with the number of delay hours produced by the system is proposed. To propose quantifications of the relationship between the assumed causes and delays, regression models were developed using regu- lar least-square models and the GRETL software (GNU Regression, Econometric and Time-series Library). The regression coefficients have been standardized in Tables  7 and 8. Standardization of the coefficients is performed to facilitate the evaluation of the effect of each independent variable on the dependent variable. The initial calculations of the correlation coefficients for punctuality, delays and their assumed causes were presented during discussions of the task force to identify root causes and primary mechanisms explaining how the assumed causes actually influenced the railway system (and which actors were vulnerable for the various assumed causes). These are discussed further in Sect.  4. However, these discussions formed the basis for the reduced set of assumed causes of delays and low punctuality included in the regression models. Cold winter weather (represented by the indicators “number of days with less than 10  °C”, “number of days with less than 15  °C” and “number of days with more than 10 cm snowfall” and number of days with more than 10 mm precipita- tion) was identified as essential to all actors. However, although some weather- factors are significant at the 0.05-level in every model (except delays due to dis- patching 2010–2014), weather is not the dominant cause of delays at the “per month” level. The passenger operating company acknowledged that splitting up trains to use shorter trains than planned produced delays in the system and contributed to delays attributed to other actors. This finding is supported by the regression models. The variable “Reduced train length” is significant in every model except for delay hours attributed to dispatching for 2005–2009. The regression model for the sum of delay hours could be represented well by the reduced set of independent variables (R of 0.83 and 0.79). The only variable that was significant at the 0.05-level for both periods was reduced train length. Funds for investment contributed to fewer delay hours in the second period, whereas funds for operation and management contribute to delays in the model. Freight volumes (ton kilometer) and departure delays at terminal changed from being significant at the 0.01 and 0.05-level to becoming insignificant. The regression model of delay hours attributed to the Infrastructure Manager by the identical set of independent variables resulted in a good fit for the initial period 1 3 152 A. Økland, N. O. E. Olsson 1 3 Table 7 Regression models of delay hours Delay hours (sum) IM TOCs Dispatching 2005–2009 2090–2014 2005–2009 2010–2014 2005–2009 2010–2014 2005–2009 2010–2014 Constant − 5.23*** − 14.05*** − 2.85 − 9.71 − 5.28*** − 11.15*** − 8.05*** − 15.56*** Weather  Precipitation > 10 mm 0.17** − 0.12 0.21** − 0.22 0.09 − 0.03 0.16* − 0.06  Temperature < − 10 °C 0.14 0.14 − 0.09 − 0.26 0.38** 0.42*** 0.06 − 0.11  Temperature < − 15 °C 0.18 0.19 0.25 0.12 0.11 0.15 0.07 0.28  Snowfall > 10 cm 0.07 0.19** − 0.02 0.15 0.05 0.13* 0.27*** 0.15 Infrastructure manager activity  Funds for operations and maintenance 0.19 0.85*** 0.17 0.34 0.23 0.75*** 0.02 1.15***  Investment 0.24* − 1.17*** 0.30* − 0.54* 0.08 − 1.14*** 0.31* − 1.56*** Passenger transport  Train kilometers − 0.03 − 0.94*** − 0.15 − 1.54*** 0.00 − 0.40 0.22* − 0.14  Seat kilometers 0.09 1.45*** 0.17 2.11*** 0.03 0.73** 0.01 0.69* Rolling stock passenger trains  Reduced seat capacity 0.20** 0.51*** 0.17* 0.71*** 0.23*** 0.27*** 0.12 0.41*** Freight operation  Freight ton–kilometers 0.27*** − 0.09 0.14 0.25 0.31*** − 0.17* 0.35*** − 0.47***  Average departure delay from terminal 0.16** 0.06 0.16 0.11 0.12 0.02 0.17* − 0.02 R of model 0.83 0.79 0.73 0.46 0.81 0.87 0.75 0.77 Variables statistically significant at the 0.01-level are marked by a triple asterisk (***), variables statistically significant at the 0.05-level are marked by a double asterisk (**) and variables statistically significant at the 0.1-level are marked by a simple asterisk (*) Punctuality development and delay explanation factors… 153 1 3 Table 8 Regression models for punctuality Punctuality commuter trains Punctuality all passenger trains Punctuality freight trains 2005–2009 2010–2014 2005–2009 2010–2014 2005–2009 2010–2014 Constant 29.27*** 13.04** 27.98*** 34.14*** 15.61*** 12.77** Weather  Precipitation > 10 mm − 0.20* − 0.01 − 0.23** 0.13 − 0.16 0.12  Temperature < − 10 °C 0.00 0.15 − 0.08 0.16 − 0.29 − 0.33  Temperature < − 15 °C − 0.29 − 0.17 − 0.22 − 0.33 − 0.02 0.32  Snowfall > 10 cm − 0.22* − 0.08 − 0.18 − 0.18* − 0.24* − 0.14 Infrastructure manager activity  Funds for operations and maintenance − 0.04 − 0.49** 0.25 − 0.58*** 0.10 − 0.34  Investment − 0.05 0.78*** − 0.30 1.00*** − 0.07 1.08*** Passenger transport  Train kilometers − 0.06 1.10** 0.25* 0.95** 0.10 1.80***  Seat kilometers − 0.02 − 1.27** − 0.23 − 1.30*** 0.04 − 2.30*** Rolling stock passenger trains  Reduced seat capacity − 0.19 − 0.43*** − 0.24** − 0.52*** − 0.07 − 0.24* Freight operation  Freight ton-kilometers − 0.38*** 0.31 − 0.19* 0.07 − 0.40*** 0.14  Average departure delay from terminal − 0.15 0.06 − 0.26** 0.07 − 0.24* 0.01 R of model 0.60 0.55 0.66 0.70 0.56 0.66 Variables statistically significant at the 0.01-level are marked by a triple asterisk (***), variables statistically significant at the 0.05-level are marked by a double asterisk (**) and variables statistically significant at the 0.1-level are marked by a simple asterisk (*) 154 A. Økland, N. O. E. Olsson of investigation (R of 0.73). The fit between modelled and actual delay hours for the second period was significantly lower (R of 0.46). The fit between actual and modelled delay hours attributed to the passenger train operating companies was very close (R of 0.81 and 0.87). Low temperatures (num- ber of days colder than −  15  °C) was significant at the 0.05-level in both periods. The regression model for delay hours attributed to dispatching was the only one in which all assumed causes of delays and low punctuality were represented with posi- tive coefficients. Half of these signs changed in the second period. The fit of the regression models for punctuality was lower than those of the mod- els of delay hours. This is to be expected as trains may catch up to their timetable after being delayed. Three models are presented: punctuality for commuter trains, average punctuality for all passenger trains and punctuality for freight trains. The three models are quite similar with regards to significant variables and development from the initial to the second period. Weather is not presented as the main cause of low punctuality in the models. However, snowfall is significant at the 0.1-level in three models. Funds for invest- ment and funds for operations and management are significant in the second period for all three models. The same is the case for the production volume of passenger train services. Freight volumes are presented as a cause of low punctuality in the initial period of the study. However, in the latter period, the variable becomes either insignificant or appears as a factor contributing to high punctuality. 4 Discussion The original study indicated that development in delay hours in 2005–2009 was due to a combination of three factors: (1) an increased error rate in infrastructure and rolling stock, (2) extensive work close to the tracks due to new investments and an increased amount of maintenance and (3) an inability to address normal varia- tions of weather conditions. The study highlighted that the Norwegian railway had a systematic winter issue. Delays occurred to a greater extent in years with colder winters, compared to years with milder winters. In addition, construction work and activity on the tracks were related to increased delays. When construction activities increased, so did the delay hours. The increase in delay hours and lowering punctuality from 2005–2009 appeared as a year-on-year trend, with the winter of 2009/2010 at the extreme end. It was, therefore, to some extent expected that the railway’s performance would “regress to the mean” in the years following 2010. As was generally expected after record-lev- els of delays in 2009 and 2010, the following years proved to be better with regard to delays especially from 2012, as shown in Fig. 1. In the years following the investigation, a range of measures was adopted by both IM and the TOCs. These measures include extra capacity (manpower) for the removal of snow at strategically important parts of the infrastructure (especially switches), and electric heating of switches was gradually put in place. Conduc- tor rails have been installed in the Oslo tunnel to reduce the incidence of damage 1 3 Punctuality development and delay explanation factors… 155 to overhead power lines. New rolling stock was put in operation (introduced from December 2012) to serve local and regional traffic in the greater Oslo region. Addi- tionally, a new timetable was put in place in December 2013. Publicity campaigns in the form of posters at the stations and on the platforms were produced to change traveler behavior regarding how to board and alight from the train. Markings were made on the platforms to facilitate positioning for the travelers preparing to board the train, as well as making it easier for the train drivers to stop at the appropriate place at the platform. Five years later, some of the measures taken are perceived as being highly suc- cessful, whereas the measures that were expected to have the greatest effect have yet to produce extensive results. The effects of the measures taken can be evaluated by analysing data for the period 2010–2014 by extending the time series and reviewing the correlation and regression series. In the following sections, we discuss in more detail the extent and the mecha- nisms of how the assumed causes of delays and low punctuality affect the rail system to produce delays. This analysis can be used as an ex post analysis of the effects of implemented measures, and especially the combined effects and their influence on the whole railway system. The regression models are suitable to identify how rela- tionships between assumed causes and the assumed resulting low punctuality and delays have changed. The measures that have been put in place vary with regards to when and how gradually they have been introduced. Some, such as the introduction of a new timetable, are in operation from a fixed date. Others, such as the introduc- tion of new rolling stock, have been gradually introduced over several years. 4.1 Winter—variations in weather The various seasons each introduce distinct challenges for rail operations, such as frost heaving in early spring, sun kink during summer, and defoliation dur- ing autumn. Figure  1 reveals that the Norwegian railway has systematic winter issues.  Every year sees a dip in punctuality during winter and an increase in both delay hours and the number of cancellations. One may expect trouble to occur in periods with especially severe weather, as is the case with other modes of trans- portation. It appears, however, that it is not only the “extreme” weather that causes problems for Norwegian railways but also regular winter. Only winters that are exceptionally mild have seen rail operations performing in line with the norm for the rest of the year. The regression models only partially support the notion that weather is an impor- tant cause of delays and low punctuality. There may be several explanations as to why that is. One is the resolution in the analyses. Instances of “bad” or extreme weather rarely last for months. Still, every model (with two exceptions for the sec- ond period) includes at least one weather-variable that is significant at the 0.01-level. There were two distinct issues with winter operations that concerned the repre- sentatives from the IM and TOCs. One was the failure rate of switches and cross- ings, which increased due to ice forming and obstructing them from locking in posi- tion. The second was snow on the rolling stock melting when trains passed through 1 3 156 A. Økland, N. O. E. Olsson tunnels, to re-freeze once the trains left the tunnels. Both were of special impor- tance in the Oslo area. There has been an increase in the rate of introducing electric heating to switches and crossings after 2010. The number of tunnels, on the other hand, is also increasing because new railway lines in densely populated areas tend to require lines to run underground. The study indicates that the snow has a stronger impact on the punctuality at the final destination than on the number of delay hours, whereas low temperature is more important for delays. The correlations between snowfall and low temperature on the one side and goods freight and passenger traffic on the other were similar in magnitude, implying that freight and passenger traffic are somewhat equally influ- enced by winter conditions. 4.2 Infr astructure manager activity The investigation focused on infrastructure manager activity rather than instances of infrastructure failures. Infrastructure failures (and partial failures) may result in temporary speed restrictions, a full stop of all traffic or no effect at all on traffic. Old infrastructure is usually more prone to failures than new (after the initial run-in period). When failures occur, identifying, getting to and locating the failure sources often take more time than the repairs. However, the data on infrastructure condition and the number of failures were not significant when introduced in the regression model for 2005–2009. The corresponding data for 2010–2014 was not evaluated in the ex post investigation. Infrastructure failures are probably still relevant, for exam- ple, as part of the mechanism in which the weather influenced the number of delay hours. Instead, a hypothesis was put forward that increased infrastructure manager activ- ity, with the aim of reducing the number of delays and increase capacity on the net- work through operations, maintenance activities, investment projects, and upgrades, which were a cause for delays and low punctuality. The study documented the unfortunate link between action to reduce delays and the amount of delays in the railway system for the period 2005–2009. Maintenance activities and investment in upgrading infrastructure, as well as the construction of new infrastructure, contributed significantly to delays in the period up to 2009. The amount of IM operation and maintenance and construction work increased rather than decreased in the years following 2010. Still, both the correlation and regres- sion models indicated a reversal in the relationship between investment and delays and low punctuality for the second period. This raises questions regarding the causal relationship between construction (investment), operations and maintenance and delays and low punctuality. The causal relationships are multi-faceted and are expected to include: 1. Low punctuality. This highlights the need for increased maintenance and invest- ments in the infrastructure (indicating that funds for construction and maintenance lag the development in punctuality). 1 3 Punctuality development and delay explanation factors… 157 2. Ongoing work (both construction and maintenance). This affects traffic due to the introduction of speed restrictions and capacity limitations as work is conducted. The effect will increase in cases where the timetable is not adjusted according to current capacity/speed limits. 3. Punctuality levels. These increase after work has been performed, but mainly after a run-in period for new infrastructure and after new times are introduced, as shown by Olsson (2006). During construction close to infrastructure in operation, as well as some main- tenance work, temporary speed restrictions are put in place. Speed restrictions increase travel time, reduce capacity and remove buffers on the network. From 2010, additional care has been taken to ensure sufficient buffers in the timetables for lines where investment projects were expected to take place. Additional measures to avoid investment, operations and maintenance resulting in delays and low punctuality include executing these in periods with less traffic (summer, nights and weekends). Even with these measures in mind though, it should not be expected that invest- ments actually work as buffers against delays; some elements of chance or some confounding factors are more probably in play. 4.3 Passenger transport and rolling stock Reduced seat capacity showed a strong correlation (between 0.49 and 0.66) with the total number of delay hours, delay hours attributed to the main passenger train operator and delay hours attributed to dispatching. Reduced seat capacity due to shorter trains was only studied for passenger trains. Splitting of double sets would often result in a reduced number of seats and available doors to board and step off the train, and hence the need for longer stops at stations. In addition to reduced seat capacity, shorter trains may also mean that passengers standing along the full plat- form length may need to walk along the platform to board. The total number of pas- senger train kilometers was also identified as being correlated with the number of delay hours attributed to the IM. In the regression models presented in Tables  7 and 8, a reduced train length (compared with the planned number) resulted in an increased number of delay hours attributed to the infrastructure manager as well as to the operator for both passenger and freight trains. This result was expected for passenger trains but not for freight trains and caused a debate in the task force. Periods in which there were less split- tings of trains also saw reductions in the number of delay hours attributed to the infrastructure manager, which may indicate that splitting trains is a way of reduc- ing the inconvenience of passengers when severe delays have occurred and rolling stock is not in a position to execute the timetable as planned, independent of who is responsible for the initial delays. 1 3 158 A. Økland, N. O. E. Olsson 4.4 Freight The total ton-kilometers (the product of tons of goods and the number of kilometers it was transported) was identified as significant for overall delay hours as well as for passenger operators’ and goods freight operators’ delay hours. The regression models support the notion of freight ton-kilometers as a factor contributing to delays and low punctuality only in the initial period. In the second period, the relationship appeared to be reversed, with the exception of delay hours attributed to the infra- structure manager. Freight trains do not disturb regular traffic as long as they keep up with their schedule. If they do not, the single-tracks of the Norwegian railway system result in delays, with the risk of spreading to the rest of the network. Freight train punctuality effectively illustrates the vulnerability of the rail system. Departure punctuality from the freight terminal has, therefore, traditionally been treated as an essential issue. Departure punctuality is closely related to “freight train ready at terminal”, which is logged by the freight operator. Sufficient turnaround times, available personnel and lift capacity are key factors to address for the opera- tors to ensure punctual departure. However, the variables “ready at terminal” and “average departure delay from terminal” are significant in a lower number of the regression models than might have been expected. A possible explanation lies in the nature of using averages. Higher resolution for the data (for instance average depar- ture delay and delay hours per day) will probably provide additional insight into the relationship between departure delays and performance on the rail network. 5 Conclusion The paper has documented a revisit of an investigation into causes of delays and low punctuality in the Norwegian train system. Enabled by new data on performance in the years following the initial analysis, new analyses provide the grounds for re-eval- uating the original findings. Appending data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality has changed as various measures have been put in place, the same factors remain influential: low temperature (< − 10 °C and < − 5 °C) and snowfall (> 10 cm), reduced train lengths (mainly due to running single rather than double sets of rolling stock) and increased volume of train services (freight and passenger trains) still contribute to delays and low punctuality. The relationship between infrastructure management activity (oper- ations, maintenance and investment) and delays and punctuality has been reversed in the models for the second period. In the first period, more activity was correlated with more delays, while this was not the case in the second period. The scientific contribution of this paper is related to two aspects. First, we con- tribute to the literature on empirical analyses of delay causes. Second, we illus- trate an approach for ex post evaluation of effects from punctuality improvement initiatives. 1 3 Punctuality development and delay explanation factors… 159 Acknowledgements Open Access funding provided by NTNU Norwegian University of Science and Technology (incl St. Olavs Hospital - Trondheim University Hospital). The authors would like to thank everyone who contributed to the analyses from Jernbaneverket, NSB, CargoNet and Flytoget (the Airport Express Train). Open Access This article is licensed under a Creative Commons Attribution 4.0 International License, which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Com- mons licence, and indicate if changes were made. The images or other third party material in this article are included in the article’s Creative Commons licence, unless indicated otherwise in a credit line to the material. If material is not included in the article’s Creative Commons licence and your intended use is not permitted by statutory regulation or exceeds the permitted use, you will need to obtain permission directly from the copyright holder. To view a copy of this licence, visit http://creat iveco mmons .org/licen ses/by/4.0/. References Andersson E (2014) An economic evaluation of the swedish prioritisation rule for conflict resolution in train traffic management. Proc Soc Behav Sci 111:634–644. https ://doi.org/10.1016/j.sbspr o.2014.01.097 Andersson EV, Peterson A, Törnquist Krasemann J (2013) Quantifying railway timetable robustness in critical points. J Rail Transp Plan Manag 3(3):95–110. https ://doi.org/10.1016/j.jrtpm .2013.12.002 Bender M, Büttner S, Krumke S (2013) Online delay management on a single train line: beyond competi- tive analysis. Plan Oper 5(3):243–266. https ://doi.org/10.1007/s1246 9-013-0070-z Benezech V, Coulombel N (2013) The value of service reliability. Transp Res Part B 58(C):1–15. https :// doi.org/10.1016/j.trb.2013.09.009 Bergström A, Krüger N (2013) Modeling passenger train delay distributions—evidence and implications. IDEAS Working Paper Series from RePEc Carey M, Carville S (2003) Scheduling and platforming trains at busy complex stations. Transp Res Part A: Policy Pract 37(3):195–224. https ://doi.org/10.1016/S0965 -8564(02)00012 -5 Coulombel N, De Palma A (2014) Variability of travel time, congestion, and the cost of travel. Math Popul Stud: Risky Time Prospects Travel Demand 21(4):220–242. https ://doi.org/10.1080/08898 480.2013.83642 0 Enno Wiebe L (2010) Factsheet snow and ice. Retrieved April 21, 2011, from UIC Information Platform “Winter and Railways” Gibson S, Cooper G, Ball B (2002) The evolution of capacity charges on the UK rail network. J Transp Econ Policy 36(2):341–354 Gorman MF (2009) Statistical estimation of railroad congestion delay. Transp Res Part E: Logist Transp Rev 45(3):446–456. https ://doi.org/10.1016/j.tre.2008.08.004 Hadiuzzaman M, Malik DMG, Barua S, Qiu TZ, Kim A (2019) Modeling passengers’ perceptions of intercity train service quality for regular and special days. Public Transp 11(3):549–576. https ://doi. org/10.1007/s1246 9-019-00213 -0 Hansen IA, Pachl J (2008) Railway timetable and traffic: analysis. Modelling, Simulation, Eurailpress, Hamburg Harris NG, Godward EW (1992) Planning passenger railways: A handbook. Derbyshire Transport Publish- ing Company Limited, Glossop Harris NG, Mjøsund CS, Haugland H (2013) Improving railway performance in Norway. J Rail Transp Plan Manag 3(4):172–180. https ://doi.org/10.1016/j.jrtpm .2014.02.002 Heinz W (2003) Passenger service times on trains. KTH Royal Institute of Technology, Stockohlm Huang Y, Dong Y, Zhao Y-K (2011) Simulation study of temporary speed restriction on train operation. J Railw Signal Commun 47(1):13–15 Jernbaneverket (2015) Jernbanestatistikk 2015. https ://www.jernb anedi rekto ratet .no/globa lasse ts/docum enter /jernb aneve rket-stati stikk -2015.pdf. Accessed 19 May 2020 König E (2020) A review on railway delay management. Public Transp. https ://doi.org/10.1007/s1246 9-020- 00233 -1 1 3 160 A. Økland, N. O. E. Olsson Kristoffersson I, Pyddoke R (2019) A traveller perspective on railway punctuality: passenger loads and punc- tuality for regional trains in Sweden. Paper presented at the RailNorrköping 2019. 8th international conference on railway operations modelling and analysis (ICROMA), Norrköping, Sweden, June 17th– 20th, 2019 Kroes E, Kouwenhoven M, Duchateau H, Debrincat L, Goldberg J, Kroes E (2007) Value of punctuality on suburban trains to and from Paris. Transp Res Rec 2006:67–75. https ://doi.org/10.3141/2006-08 Lam TC, Small KA (2001) The value of time and reliability: measurement from a value pricing experiment. Transp Res Part E 37(2):231–251. https ://doi.org/10.1016/S1366 -5545(00)00016 -8 Li Z, Hensher DA, Rose JM (2010) Willingness to pay for travel time reliability in passenger transport: a review and some new empirical evidence. Transp Res Part E 46(3):384–403. https ://doi.org/10.1016/j. tre.2009.12.005 Liu H, Lu H, Lu M, Zhang J (2009) Study on the system design and optimal models of urban rail transit traction calculation system. In: ICCTP 2009: critical issues in transportation systems planning, develop- ment, and management, pp 1–7) Ludvigsen J, Klæboe R (2014) Extreme weather impacts on freight railways in Europe. Nat Hazards 70(1):767–787. https ://doi.org/10.1007/s1106 9-013-0851-3 Monchambert G, de Palma A (2014) Public transport reliability and commuter strategy. J Urban Econ 81(1):14–29. https ://doi.org/10.1016/j.jue.2014.02.001 Noland RB, Polak JB (2002) Travel time variability: a review of theoretical and empirical issues. Transp Rev 22(1):39–54. https ://doi.org/10.1080/01441 64001 00224 56 Norheim B, Ruud A (2011) The underestimated demand for public transport? Paper presented at the Euro- pean transport conference 2011 association for European transport (AET) transportation research board Nyström B (2008) Aspects of improving punctuality: from data to decision in railway maintenance. PhD thesis. Luleå University of Technology Olsson NOE, Haugland H (2004) Influencing factors on train punctuality—results from some Norwegian studies. Transp Policy 11(4):387–397. https ://doi.org/10.1016/j.tranp ol.2004.07.001 Olsson N, Økland A, Veiseth M, Stokland Ø (2010) Driftsstabilitet på Jernbaneverkets nett—årsaksanalyser 2005–2010. Punktlighets- og regularitetsutviklingen, gransking av årsaker. SINTEF, Trondheim Palmqvist C-W (2019) Delays and timetabling for passenger trains, vol 317. PhD thesis. Lund University, Lund Palmqvist C-W, Tomii N (2019) Overtakes and dwell time delays for Japanese commuter trains. In: 15th world conference on transportation research, Mumbai, India Palmqvist C-W, Olsson N, Hiselius L (2017) Delays for passenger trains on a regional railway line in South- ern Sweden. Int J Transp Dev Integr 1(3):421–431. https ://doi.org/10.2495/TDI-V1-N3-421-431 Palmqvist C-W, Tomii N, Ochiai Y (2020) Explaining dwell time delays with passenger counts for some commuter trains in Stockholm and Tokyo. J Rail Transp Plan Manag. https ://doi.org/10.1016/j.jrtpm .2020.10018 9 (in press, corrected proof) Parbo J, Nielsen OA, Prato CG (2016) Passenger perspectives in railway timetabling: a literature review. Transp Rev 36(4):500–526. https ://doi.org/10.1080/01441 647.2015.11135 74 Paulley N, Balcombe R, Mackett R, Titheridge H, Preston J, Wardman M, White P (2006) The demand for public transport: the effects of fares, quality of service, income and car ownership. Transp Policy 13(4):295–306. https ://doi.org/10.1016/j.tranp ol.2005.12.004 Rietveld P, Bruinsma FR, van Vuuren DJ (2001) Coping with unreliability in public transport chains: a case study for Netherlands. Transp Res Part A 35(6):539–559. https ://doi.org/10.1016/S0965 -8564(00)00006 -9 Salkonen R, Paavilainen J (2010) Measuring railway traffic punctuality from the passenger’s perspective. Paper presented at the general proceedings of the 12th world conference on transport research (WCTR), Lisbon, Portugal, July 11–15, 2010 Seco A, Gonçalves J (2007) The quality of public transport: relative importance of different performance indicators and their potential to explain modal choice. Urban transport XIII: urban transport and the environment in the 21st century, pp 313–325 Sørensen AØ, Bjelland J, Bull-Berg H, Landmark AD, Akhtar MM, Olsson NOE (2018) Use of mobile phone data for analysis of number of train travellers. J Rail Transp Plan Manag 8(2):123–144. https :// doi.org/10.1016/j.jrtpm .2018.06.002 Szafránski Z (2011) Winter and railways-study. Retrieved from UIC website: http://www.uic.org/forms /IMG/ pdf/500_uic_siafi _repor t__winte r_and_railw ays.pdf Takeuchi Y, Tomii N, Hirai C (2007) Evaluation method of robustness for train schedules. Q Rep RTRI 48(4):197–201. https ://doi.org/10.2219/rtriq r.48.197 1 3 Punctuality development and delay explanation factors… 161 Tomii N (2010) How the punctuality of the Shinkansen has been achieved. WIT Trans Built Environ 114:111–120. https ://doi.org/10.2495/CR100 111 Trafikverket (2010) Utredning Järnväg Vinter. Situationen för järnvägen under vintern 2009/10—Trafikver - ket, Borlänge van Hagen M, Sauren J (2014) Influencing the train experience: using a successful measurement instrument, vol 1, pp 264–275 Vromans M (2005) Reliability of railway systems. Erasmus University, Rotterdam Wallander J, Mäkitalo M (2012) Data mining in rail transport delay chain analysis. Int J Shipp Transp Logist 4(3):269–285. https ://doi.org/10.1504/IJSTL .2012.04749 2 Wang P, Zhang Q-P (2019) Train delay analysis and prediction based on big data fusion. Transp Saf Environ 1(1):79–88. https ://doi.org/10.1093/tse/tdy00 1 Wardman M (2001) A review of British evidence on time and service quality valuations. Transp Res Part E 37(2):107–128. https ://doi.org/10.1016/S1366 -5545(00)00012 -0 Wenyi J, Xin C, Zhangdui Z (2010) The impact of quality of services in chinese train control system on train delays analysis. In: 2010 IEEE 72nd vehicular technology conference—fall, September 2010, pp 1–5 Xia Y, Van Ommeren JN, Rietveld P, Verhagen W (2013) Railway infrastructure disturbances and train operator performance: the role of weather. Transp Res Part D: Transp Environ 18:97–102. https ://doi. org/10.1016/j.trd.2012.09.008 Zakeri G, Olsson NOE (2017) Investigation of punctuality of local trains—the case of Oslo area. Transp Res Proc 27:373–379. https ://doi.org/10.1016/j.trpro .2017.12.080 Zhou Y, Mi C (2013) Modeling and simulation of train movements under scheduling and control for a fixed-block railway network using cellular automata. Simulation 89(6):771–783. https ://doi. org/10.1177/00375 49713 48740 3 Publisher’s Note Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations. 1 3 http://www.deepdyve.com/assets/images/DeepDyve-Logo-lg.png Public Transport Springer Journals

Punctuality development and delay explanation factors on Norwegian railways in the period 2005–2014

Public Transport , Volume 13 (1) – Jun 9, 2020

Loading next page...
 
/lp/springer-journals/punctuality-development-and-delay-explanation-factors-on-norwegian-oZ93gKvuAU

References (51)

Publisher
Springer Journals
Copyright
Copyright © The Author(s) 2020
ISSN
1866-749X
eISSN
1613-7159
DOI
10.1007/s12469-020-00236-y
Publisher site
See Article on Publisher Site

Abstract

The paper revisits an investigation of delays and punctuality on Norwegian rail- roads from 2010, re-evaluating its findings and studying the effects of later measures put in place between 2010 and 2014. Norwegian railways saw a steady decline in punctuality from 2005–2010, prompting the establishment of a task force to under- stand the trends and patterns behind the delays on the network. Data was collected on punctuality and delays, as well as on factors that were likely causes of delays. The original study pointed to three main areas that cause delays during the period 2005–2009: (1) an increased error rate in infrastructure and rolling stock, (2) exten- sive work close to the tracks due to increased maintenance and renewals and (3) an inability to perform consistently even under normal weather conditions. Meas- ures were put in place to turn around the overall performance. Appending data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality changed as these measures have been put in place, some fac- tors remained influential: low temperature (< − 10 °C and < − 15 °C) and snowfall (> 10 cm), reduced train lengths and increased volume of train services (both freight and passenger trains) still contribute to delays and low punctuality. The paper con- tributes to the literature on empirical analyses of delay causes. However, it can also be read as an illustration of an approach for an ex post evaluation of effects from punctuality improvement initiatives. Keywords Punctuality analysis · Railway · Delays · Causes 1 Introduction This paper documents a revisit of an analysis of the punctuality of Norwegian rail- roads from 2010. In the expanded study, carried out 5  years after the initial inves- tigation, we looked into assumed causes of delays and low punctuality with the * Nils O. E. Olsson nils.olsson@ntnu.no Norwegian University of Science and Technology, 7491 Trondheim, Norway Vol.:(0123456789) 1 3 128 A. Økland, N. O. E. Olsson additional data from the period 2010–2014. The original study (Olsson et al. 2010) indicated that development in the delay hours in 2005–2009 was due to a combina- tion of three factors: (1) an increased error rate in infrastructure and rolling stock, (2) extensive work close to the tracks due to new investments and an increased amount of maintenance and (3) an inability to address normal variation of weather conditions. Following the initial investigation, several measures were put in place by several actors in the Norwegian Railway sector (infrastructure manager, passenger and freight train operators) in order to improve performance. Via correlation and regression analyses for the two periods, the article contributes to the scientific litera- ture on empirical analyses of delay causes by presenting a double investigation into causes of delays and low punctuality, as well as an approach for an ex post evalua- tion of effects from punctuality improvement initiatives. The revisit, enabled by new data on performance in the years following the analy- sis, provides a rare opportunity for re-evaluating the original findings. 1.1 Q uality indicators for railway performance: punctuality and delays Punctuality is an important element in the quality of service for both passenger and freight transport on railways. Several studies have shown that punctuality is of criti- cal significance to the customer satisfaction of railway travellers (Lam and Small 2001; Norheim and Ruud 2011); Salkonen and Paavilainen (2010). Punctuality is claimed to be one of the most important quality indicators in railroad operations (Nyström 2008; Seco and Gonçalves 2007). Several studies have concluded that punctuality is highly valued among railway customers (Andersson 2014; Coulombel and De Palma 2014; Kroes et  al. 2007; Palmqvist et  al. 2017; Paulley et  al. 2006; Rietveld et al. 2001; Wardman 2001). Li et al. (2010) found that travellers are willing to pay more for their fare in exchange for a reduction in travel time variability. Kroes et  al. (2007) highlight that in the greater Paris area, creating new infrastructure to develop the public transport network is of no use if the existing network is not of high quality. Hadiuzzaman et al. (2019) found that the perceived service quality for train travellers is related to both physical conditions and service of intercity trains. Monchambert and de Palma (2014) model the influence of punctuality on mode choice of commuters, illustrating that punctuality influences the choice between bus and train. According to van Hagen and Sauren (2014), NS (Nederlandse Spoorwe- gen) has developed a pyramid of customer preferences. The base of the pyramid is formed by the basic needs of reliability and safety. They describe punctuality (or reliability) as a “dissatisfier”, meaning that this quality aspect is rated negatively if it does not meet expectations. If the desire for punctuality is met, the passenger will experience a sense of control and be satisfied with the journey (but no more than that). Punctuality and delays are most often mentioned as similar terms but have differ - ent meanings. Delays are measured in time units, whereas punctuality is expressed through percentage. Parbo et al. (2016) say that punctuality, as a numerical measure- ment, is the percentage of trains arriving on time to the stations. To measure punctu- ality, one must define the threshold for when an arrival is counted as a delay. These 1 3 Punctuality development and delay explanation factors… 129 registration limits vary from country to country. For example, in Germany, the UK and the Netherlands, the delay limits are 5, 10 and 3 min, respectively (Hansen and Pachl 2008). In Japan, a train is considered delayed if it is more than 1 min behind schedule (Tomii, 2010). In Norway, a local train is on time if it reaches the destina- tion with less than 4 min (3 min and 59 s) delay, whereas a long-distance train is on time if it reaches the destination with less than 6 min (5 min and 59 s) delay. The 3 and 5  min limits used in Norway trace their origin to a time when punc- tuality was measured manually and in full minutes at the final destination of each train. Trains being more than 3 and 5 min delayed were considered as non-punctual. This was calculated as “>3” and “> 5” minutes and discussed as if the limits were 3 and 5 min, but these were actually in effect “≥ 4” and “≥ 6” minutes. To maintain consistency when delays came to be measured in seconds, the limits became 3 min and 59  s and 5  min and 59  s, respectively. Punctuality can be measured in several ways. The most common is based on arrival delay to the final destination (Parbo et  al. 2016), which is discussed above. Depending on data availability, which has been increasing in recent years (Wallander and Mäkitalo 2012), it is also possible to measure punctuality at any station (Palmqvist 2019). An alternative measure of delay is travel time variability (Noland and Polak 2002; Rietveld et  al. 2001), which is especially relevant for train traffic that is to a lesser extent based on timetables, such as some kinds of freight trains (Gorman 2009). While punctuality is typically measured based on the number of trains being delayed, Salkonen and Paavilainen (2010) call for a refocus of punctuality measures from the number of trains affected, to how (and how many) passengers are affected. This would mean to shift focus from train punctuality to traveller punctuality (Krist- offersson and Pyddoke 2019). While this may be a better measure of the railway sys- tem performance in terms of a user perspective, it is often a challenge to obtain data on passenger volumes (Sørensen et  al. 2018). An alternative approach is to study train interactions, and especially the share of interactions that occur as planned (Palmqvist and Tomii 2019). König (2020) provides a taxonomy scheme for railway punctuality problems and connects the field of delay management to other parts of the planning process. There are several approaches to research on punctuality, including optimization of timetables (Andersson et al. 2013) analysing historical traffic data (Benezech and Coulombel 2013; Takeuchi et  al. 2007) and studying timetable supplements (Vro- mans 2005). Another tradition is to study delay causes. This paper continues this lat- ter tradition. In the following, we give a brief overview of some research in the field. 1.2 P revious studies on causes of delays and low punctuality Harris and Godward (1992) listed five variables that affect the punctuality of trains and investigated their correlations to punctuality for three British datasets (InterCity, Network SouthEast and Regional) and one Dutch dataset. The study showed that two variables were statistically significant in determining punctuality, distance cov - ered from departure station and train length (in number of carriages). The other fac- tors investigated were: the previous number of station stops, age of a motive power 1 3 130 A. Økland, N. O. E. Olsson unit and track occupation. Ten years later, a similar study was performed on data from Norwegian railways by Olsson and Haugland (2004) and presented the correla- tion between delays and punctuality and the following factors: Number of travellers, Load factor (number of passengers/seats), Capacity utilization of tracks, Cancellations, Speed restrictions, Development close to tracks, Departure and arrival punctuality, Regulations for handling exceptions. The factors with the strongest correlation to punctuality were the number of trav- ellers, the load factor of the trains and departure punctuality. The impressions of practitioners had led to the authors expecting a stronger correlation than what was actually found between punctuality and capacity utilization and the reduction of speed. The weak degree of correlation seen in Olsson and Haugland (2004) led to new hypotheses regarding the relationship between the studied factors and punctual- ity. Rather than having a linear effect on punctuality, the various factors are expected to have threshold values. If thresholds are exceeded, punctuality is affected. Factors, such as capacity utilization and speed restrictions, can have such thresholds. If the thresholds are not exceeded, the effect of these factors is often hidden in the noise from other factors. Passenger behavior and numbers have been studied as an explanatory factor for delays (Heinz 2003; Palmqvist et al. 2020). Carey and Carville (2003) also highlight the importance of how train stations can influence punctuality. Harris et al. (2013) state that the time required for passenger boarding and alighting at stations is a criti- cal element of overall train service performance. Bender et al. (2013) studied how to manage an unknown number of passengers that want to board a train, the objective being to minimize the total delay of all passengers. Bergström and Krüger (2013) state that a major share of all delay time is associ- ated with the tail of the delay distribution. Thus, extreme delays cannot be neglected when prioritizing between measures designed to improve rail infrastructure. Berg- ström and Krüger (2013) also claim that delays are not only concentrated in size but are concentrated in space and time and follow a precise power law with respect to days and an exponential distribution with regard to stations. In terms of punctuality, their study showed that large and small delays had an equal influence on the overall punctuality (assuming a small delay is more than the delay threshold of 4 min). Several European studies have looked into the effects of severe weather condi- tions as a potential explanation for delays. Xia et  al. (2013) studied how weather conditions affect train operator and railway infrastructure performance in the Nether - lands. Their study documented that wind gusts, snow, precipitation, temperature and leaves had strong positive effects on the number of infrastructure disruptions, and a strong effect on train arrival punctuality and cancellation rates. Several weather- related aspects, such as snow, leaves, high temperatures and variation in temperature 1 3 Punctuality development and delay explanation factors… 131 within the day, have negative impacts on punctuality and cancellation rates. Their impacts are, in general, indirect by causing disturbances in the railway infrastruc- ture. Gusts, precipitation and low temperatures, on the other hand, have both direct and indirect effects. Ludvigsen and Klæboe (2014) presented four cases of how the harsh 2010 winter weather affected rail freight operations in Norway, Sweden, Swit- zerland and Poland. The study emphasized the reactive behavior of rail managers who mobilized to reduce the adverse outcomes. During the snowy and cold winter of 2009/2010, many problems occurred. Eleven countries experienced rolling stock problems (Enno Wiebe 2010). According to Szafránski (2011) and Trafikverket (2010), problems that occurred in Sweden were related to four different areas: infra- structure, contractor capacity, internal management and process, and public relations with passengers and operators. More recently, Wang and Zhang (2019) found that severe weather was strongly influencing train delays. Railway capacity has been widely assumed to be an important factor regarding train punctuality, especially concerning the volume of secondary delays. Gibson et al. (2002) undertook an extensive study on the relationship between capacity utili- zation and delays in the UK. Their aim was to find empirical justification for conges- tion charges on the parts of the railway network with the highest capacity utilization. Wenyi et  al. (2010) studied delays on Chinese high-speed railways, with a special focus on delays caused by the train control system; they found the train control sys- tem accounted for 10% of total delays of 5 min or more. The availability of large amounts of data from railway systems has resulted in more analyses of punctuality and delays, laying the foundations for enhanced timeta- bling, simulations, driver assistance and train dispatching. Examples include Huang et al. (2011) and Zhou and Mi (2013), who analysed the effect of speed restrictions based on simulations. Liu et al. (2009) discuss optimal driving patterns on lines with speed restrictions. In summary, in the railway literature there is a large tradition of simulation-based approaches for timetable and punctuality analyses. We have briefly reviewed empiri- cal studies that investigate factors that influence punctuality. Common factors that are analysed in such studies include weather, availability of infrastructure and roll- ing stock, capacity utilization, passenger behavior and train dispatching. 1.3 Notes on special characteristics of Norwegian railways The Norwegian railway network consists of railway tracks that extend to 4087  km across the country from North to South. There are 2622  km of electrified tracks, 242 km of double-tracks, 60 km of high-speed tracks, 696 tunnels and 2760 bridges (Jernbaneverket 2015). Two special features of the network are the relatively low share of double-tracks and high share of non-electrified railway (38% is not elec- trified). The major tracks for long-distance, regional and freight trains are single- tracked. Nearly all double-tracks are located in the larger Oslo-area, where there is a continuous construction of new double-tracked lines. The Oslo area is important for the rail traffic for two reasons: the majority of trains (with the majority of travellers) 1 3 132 A. Økland, N. O. E. Olsson run there, and train traffic in the Oslo area affects the trains in large parts of the country. Two different measurements related to delays are used in Norway. One is related to delays to the final destination and is a measurement of time or percentage of trains that are considered as delayed. The other measure is related to registered delay causes. When trains are more than 4 min delayed or additionally delayed, train dis- patchers are required to register a delay cause. Delays are registered while under way, and a train number can get several registrations of additional delays. These delays are summarized and referred to as delay hours. A train may hence accumu- late delay hours even though it arrives punctually at the final destination. The delay hours are allocated to operators, infrastructure or traffic management. 1.4 Development in overall punctuality: 2005–2010 The number of delay hours allocated to passenger trains was largely on a steady rise from 2005 to 2010. There was an increase in most categories for the period as a whole. For the operators on the Drammen–Eidsvoll route (mainly NSB and the Airport express train), the number of delay hours remained stable until the win- ter of 2009–2010. The winters of 2007 and 2009 also showed an increase in delay hours, but the variation in delay hours during the year remained remarkably stable. The winter of 2009–2010 stands out as having a higher peak in the number of delay hours and that it took longer for the number of monthly delay hours to return to nor- mal levels. For the infrastructure manager, the situation with regards to delay hours gradu- ally deteriorated over the period from 2005 to 2010. In addition to an increase in the average number of delay hours from year to year, the variation from week to week also increased significantly.  The winter of 2009–2010 was a continuation of the trend regarding the number of delay hours for the infrastructure manager. 1.5 Measur es taken from 2010 Several efforts were put in place to improve the reliability of the rail system from 2010. Some measures were relatively straightforward: extra capacity (manpower) for removal of snow at strategically important parts of the infrastructure (especially switches), and electric heating of switches was gradually put in place. Conductor rails were installed in the Oslo tunnel to reduce the tearing down of the overhead power line. New rolling stock was put in place (introduced from December 2012) to serve local and regional traffic in the greater Oslo region. Additionally, a new timetable for the greater Oslo area was put in place in December 2013 as well. Publicity campaigns in the form of posters at the stations and on the platforms were produced to change traveller behavior regarding how to board and alight from the train, as described by Harris, Mjøen and Haugland. Markings were made on the platforms to facilitate positioning for the travellers preparing to board the train, as 1 3 Punctuality development and delay explanation factors… 133 well as making it easier for the train drivers to stop at an appropriate place at the platform. Finally, the funds dedicated to operations and maintenance for the Infrastructure Manager has increased year-by-year throughout the period (as well as the funds for infrastructure investment). 1.6 Development in overall punctuality: 2010–2014 The years 2009 and 2010 stand out as years of crisis for Norwegian railways. In what has been regarded as an “annus horribilis”, many of the things that could go wrong did go wrong. The cold winter and the large number of delays ensured an increased focus on robustness in case similar conditions were to occur again. Fig- ure 1 shows the delay hours on Norwegian railways in the period from 2005 to the end of 2014. The years following 2010 have a similar volume of delays as the years prior to 2010. 2 Methods 2.1 The task force and its mandate Following an initiative from the Ministry of Transportation, a task force consisting of representatives from the infrastructure manager (IM), three train operating com- panies (TOCs) for people transport, and the largest goods operator was established to review the development in punctuality and delay hours over the period from 2005 to the winter of 2009/2010. In the year 2005, registration of punctuality and delay hours-registration was automated (although the tagging of delay-codes remained a manual task). Therefore, 2005 was a natural starting point for the review. The intro- duction of automated registration coincided with the highest average punctuality level registered for the Norwegian railways. A team of two researchers was engaged to organize and facilitate four workshops with the task force and to conduct analyses between each session using data pro- vided by the participants. The analyses laid the groundwork for the task force’s work on identifying the causes for delays and causes to reduce the amount of yearly delay hours and to increase punctuality. The following was defined as a mandate for the work: “Reviewing developments in delay hours and identify the underlying root cause(s) as for why the trend shows a steadily deteriorating development from 2005 until now (2010). This includes inves- tigating potential connections with changes in operating conditions and traffic vol- ume. Recognized statistical methods are to be used. Special in-depth analyses can be performed on identified problem areas or the implementation of measurements in areas where data are not available.” The participating TOCs and the IM willingly shared their data, under the pre- requisite that sensitive data should remain with the researchers and that all analyses would be presented to the task force (a list of the data used is included in Sect. 2.2). 1 3 134 A. Økland, N. O. E. Olsson 1 3 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 Fig. 1 Delay-hours per month and three-month moving average for the Norwegian railways (sum of delays for goods and passenger trains) from 2005–2014. Values are indexed. 100 equals average number of delay hours per month for 2000 Punctuality development and delay explanation factors… 135 The willingness to share information based on sensitive data was grounded in the understanding of a secondary, unofficial goal of the task force: Creating a shared understanding of the current status and performance of the rail system and thus cooling down an ongoing public “blame game” in the media. Analyses were con- ducted between sessions, and preliminary findings were sent to the participants for review before each meeting. Potential root causes, referred to as “assumed causes of delays and low punctuality” in the following, along with questions regarding the analyses were discussed in the group. The original task force analysis covered the period from 2005 to the first months of 2010. When we remade the analyses including the development from 2010 and onwards, we wanted to have data sets that were as comparable as possible. The analyses therefore cover two periods of five full years, January 2005 to Decem- ber 2009, and January 2010 to December 2014, in addition to analyses of the full 10-year period. Examining data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality has changed as various measures have been put in place, some factors remain influential: Low temperature (< −  10  °C and < −  15  °C) and snowfall (> 10  cm), reduced train lengths and increased vol- ume of train services (freight and passenger trains) still contribute to delays and low punctuality. The relationship between Infrastructure Management activity (opera- tions, maintenance and investment) appears to have been reversed in the second period. The overall punctuality has improved since 2010; however, the performance of the record year 2005 has not been duplicated. This paper is a continuation of the work done in the task force. We study punc- tuality-influencing factors in the period 2005 to 2009, as well as the same factors in the second period from 2010 to 2014. The paper utilizes a wider dataset and a longer time period compared to the initial study by Zakeri and Olsson (2017). 2.2 Data sources Data that captured factors which were expected to influence punctuality and delays internally and externally to the actors were collected with a resolution of per day, per week and per month. Throughout this article, the emphasis will rest on the results and the analyses of the aggregated “per month” dataset, covering the com- plete network. 2.2.1 Dependent variables: punctuality and delays Measures of punctuality and delay hours collected from 2005 to the end of 2014 were treated as dependent variables in the regression analyses. The data used for the analyses are specified in Table  1, including the dependent variables representing punctuality and delays used in the study. Punctuality was measured as the percent of trains arriving less than 4 min (local trains) or 6 min (freight and long-distance pas- senger trains) to their final destination. Delay hours were based on registered delays 1 3 136 A. Økland, N. O. E. Olsson 1 3 Table 1 Overview of dependent variables, punctuality and delay hours Punctuality aspect Indicator name Description of Indicator Unit Data source Punctuality Local passenger (NSB) Monthly punctuality for local passenger Percent trains arriving on time at final Arrival time registrations trains destination Regional passenger (NSB) Monthly punctuality for regional pas- Percent trains arriving on time at final Arrival time registrations senger trains destination Long distance passenger (NSB) Monthly punctuality for long distance pas- Percent trains arriving on time at final Arrival time registrations senger trains destination Airport express train Monthly punctuality for Airport express Percent trains arriving on time at Garder- Arrival time registrations trains moen airport Freight Monthly punctuality for freight trains Percent trains arriving on time at final Arrival time registrations destination Delay hours Infrastructure manager Delay hours registered on infrastructure Number of delay hours Delay cause registrations related delay cause codes All operators Delay hours registered on operator-related Number of delay hours Delay cause registrations delay cause codes NSB Delay hours registered as caused by NSB Number of delay hours Delay cause registrations Airport express Delay hours registered as caused by Air- Number of delay hours Delay cause registrations port express trains Freight Delay hours registered as caused by freight Number of delay hours Delay cause registrations trains Punctuality development and delay explanation factors… 137 at any point along a train route. If a train gets an increase in delay by 4 min or more between two measuring points, the cause for the delay increase is registered by the train dispatchers. The delay hour measure is the sum of these registered delays for a given line in a given time period. Punctuality and delay hours were chosen as variables because they are well estab- lished in the Norwegian railway industry. Traffic quality was measured based on these variables, and the indicators were discussed at regular quality evaluation meet- ings between the infrastructure manager and the operators. The variables, however, have some weaknesses. For example, the number of passengers is not represented in the measures. 2.2.2 Independent variables: causes of delay and low punctuality The independent variables consisted of measures of Infrastructure Manager activity (operations, maintenance and investment), volume of transport services for freight and passenger services (ton and ton-kilometers for freight operators and train and seat kilometer produced by passenger train operators) and the number of passengers. Additional independent variables related to passenger transport included changes to the type of rolling stock used for passenger trains, especially reduced seat capacity. Measures of performance at the freight terminals included departure delays from the main terminal. Factors related to weather and climate were included in the analy- ses. Weather was hypothesized to negatively influence delays and punctuality when snowfall, precipitation and low temperature hit certain thresholds. Registrations from three measuring posts in and around Oslo were collected and used in the analy- ses (Blindern, Asker and Gardermoen, respectively). The thresholds used were the number of days with – 10 °C and – 15 °C, the number of days with equal or more than 10 mm precipitation and the number of days with snowfall of 10 cm or more for each measuring post. These thresholds were defined in co-operation with the taskforce industry participants. An index was constructed for each factor combining the number of days each factor had exceeded the thresholds at each station. Table 2 is a summary of independent variables and how they are measured. The factors that were assumed to influence punctuality are a less well-established group of variables. The choice of variables was based on literature studies and previ- ous research but also based on data availability. As independent researchers, we had access to data that in general is considered to be company-internal information to the train operators. This was the case for data about passenger rolling stock avail- ability, and measures from freight terminals. Data on weather and infrastructure spending were added because both aspects were highlighted by industry representa- tives in the task force. 2.2.3 Modelling delays and punctuality Regression models of delays and punctuality on the network were developed iteratively as data were made available. The first step in the analyses consisted of calculating the correlation coefficient of the independent variables and the meas- ures of punctuality and delay hours. Correlation does not mean causation, so the 1 3 138 A. Økland, N. O. E. Olsson 1 3 Table 2 Overview of independent variables, potential drivers of delays and low punctuality Influencing factor Indicator name Description of Indicator Unit Data source Weather Days below – 10 °C Days below – 10 °C during one Number of days Weather data month Days below – 15 °C Days below – 15 °C during one Number of days Weather data month Days snowfall > 10 cm Days snowfall > 10 cm during one Number of days Weather data month Days precipitation > 10 mm Number of days precipita- Number of days Weather data tion > 10 mm during one month Infrastructure manager activity Funds for operations Yearly funds for railway infrastruc- NOK Governmental budget ture operations allocated to IM Funds for maintenance Yearly funds for maintenance rail- NOK Governmental budget way operations allocated to IM Funds for operations and mainte- Sum of yearly funds for railway NOK Governmental budget nance infrastructure operations and maintenance allocated to IM Funds for investments Yearly funds for Investments rail- NOK Governmental budget way investments allocated to IM Passenger transport Seat km tot Passenger seat-km produced by Number of km Train operators NSB in total, for the whole country Seat km Oslo Passenger seat-km produced by Number of km Train operators NSB in Oslo area Train km tot Train-km produced by NSB in Number of km Train operators total, for the whole country Train km Oslo Train-km produced by NSB in Number of km Train operators Oslo area Punctuality development and delay explanation factors… 139 1 3 Table 2 (continued) Influencing factor Indicator name Description of Indicator Unit Data source Rolling stock passenger trains Reduced seat capacity Number of departures planned Number of trains Train operator internal registrations with double or triple EMUs which are run with one EMU less than planned Rolling stock faults Number of registered rolling stock Number of trains Train operator internal registrations faults Change of rolling stock type Number of departures run with Number of trains Train operator internal registrations other type of rolling stock than planned Cancellations NSB Cancellations of NSB trains per Number of cancellations Punctuality statistics month Departure delay main terminal Departure delay main terminal Number of cancellations Freight operator internal registra- Freight operation tions Freight train ready for departure Freight train ready for departure, Minutes Freight operator internal registra- average delay tions Freight rolling stock ready from Freight rolling stock ready from Minutes Freight operator internal registra- maintenance maintenance, average delay tions Numbers from NSB AS, the former main national train operator 140 A. Økland, N. O. E. Olsson expertise of the task force was put to the test with identifying causes of delays and low punctuality. The correlation within the set of independent variables was subsequently cal- culated to investigate if the variables were internally independent. The correlation between punctuality and delay hours was calculated. In addition, one-way analyses of variance (one-way ANOVA) were carried out to further investigate the relation- ship between the weather and delay hours and punctuality. The discussions based on simple correlation factors form the basis for the regres- sion analyses and the ordinary least square models of the railway system. Three models were developed for each of the independent variables: a complete model that used the complete data set of independent variables, a model consisting of only sta- tistically significant variables in which independent variables were removed step- by-step based on their p value, and a reduced model in which only the assumed primary explanatory factors are included. The coefficients have been calculated for 2005–2009, 2010–2014 and 2005–2014. Standardized coefficients have been calcu- lated for the reduced models. The availability of relevant data combined with detailed knowledge from the participants in the task force facilitated the identification process of connections between incidents, general (known) issues and delays. The analyses are based on a data set including the assumed delay causes and potential explanatory factors, from different databases belonging to the participants (including punctuality data and maintenance records for infrastructure and rolling stock), in addition to other avail- able data sources (most importantly data on weather). The punctuality and delay data have been studied in relation to a number of possible explanatory variables to uncover correlations and causes. All of the data requested by the task force were made available. Preliminary results were presented and reviewed by the task force for quality assurance. 3 Analysis of punctuality and influencing factors 3.1 Factors influencing punctuality To begin with, we show an analysis of correlations between the different depend- ent variables and between the independent ones. Table  3 presents correlation coef- ficients (Pearson product-moment correlation coefficient or Pearson’s r) for the cor - relation between delay hours (sum and delay hours allocated to the actor responsible for the delays) and punctuality (both overall and broken down into various types of traffic). These factors are treated as dependent variables in the subsequent analyses. There is a high degree of correlation between delay hours allocated to the various actors and punctuality for different types of traffic. The correlation between delay hours and punctuality is also high, indicating that although it is possible for trains to generate delay hours while still being on time at the final destination (and hence being punctual according to the statistic), these variables are not independent of each other. 1 3 Punctuality development and delay explanation factors… 141 1 3 Table 3 Pearson product-moment correlation coefficients (Pearson’s r) of current quality measures for the railway system, Delay hours and punctuality (dependent vari- ables) Delay hours Punctuality Dispatching Infra- Sum All operators All passenger Airport Long-distance Inter-City Local trains Freight trains structure trains express passenger passenger (Oslo) manager train trains trains Delay hours  Dispatching 0.63 0.80 0.80 − 0.81 − 0.73 − 0.47 − 0.61 − 0.68 − 0.67  Infrastructure 0.63 0.84 0.57 − 0.68 − 0.61 − 0.76 − 0.80 − 0.74 − 0.60 manager  Sum 0.80 0.84 0.88 − 0.74 − 0.77 − 0.68 − 0.76 − 0.75 − 0.71  All operators 0.80 0.57 0.88 − 0.77 − 0.79 − 0.49 − 0.56 − 0.56 − 0.67 Punctuality  All passenger − 0.81 − 0.68 − 0.74 − 0.77 0.81 0.64 0.73 0.69 0.71 trains  Airport express − 0.73 − 0.61 − 0.77 − 0.79 0.81 0.48 0.64 0.60 0.62 train  Long-distance − 0.47 − 0.76 − 0.68 − 0.49 0.64 0.48 0.71 0.63 0.57 passenger trains  Inter-City pas- − 0.61 − 0.80 − 0.76 − 0.56 0.73 0.64 0.71 0.86 0.65 senger trains  Local trains − 0.68 − 0.74 − 0.75 − 0.56 0.69 0.60 0.63 0.86 0.69 (Oslo)  Freight trains − 0.67 − 0.60 − 0.71 − 0.67 0.71 0.62 0.57 0.65 0.69 Coefficients not significant at the 0.05 level are in regular font 142 A. Økland, N. O. E. Olsson 1 3 Table 4 Pearson product-moment correlation coefficients (Pearson’s r) between assumed causes of delays and low punctuality Budget Budget Budget Invest- Seat Train Seat Train Pas- Pas- Freight Freight Depar- Delay Precip- − 10 °C − 15 °C Snow- km km senger senger tonnage ton– ture ready itation fall opera- mainte- O&M ment km km tions nance total total east east volume volume kilom- delay termi- AET eters termi- nal nal Budget 1.00 0.82 0.96 0.92 0.55 0.58 − 0.90 0.52 0.86 0.88 0.73 − 0.88 0.12 0.24 0.07 0.02 0.03 − 0.24 opera- tions Budget 0.82 1.00 0.95 0.72 0.42 0.42 − 0.84 0.42 0.58 0.82 0.35 − 0.84 0.16 0.25 0.03 0.14 0.19 − 0.23 mainte- nance Budget 0.96 0.95 1.00 0.86 0.51 0.52 − 0.92 0.49 0.75 0.89 0.57 − 0.91 0.15 0.26 0.05 0.09 0.12 − 0.25 O&M Invest- 0.92 0.72 0.86 1.00 0.66 0.62 − 0.75 0.56 0.95 0.86 0.80 − 0.75 0.01 0.04 0.05 − 0.02 0.00 − 0.24 ment Seat kilo- 0.55 0.42 0.51 0.66 1.00 0.89 − 0.37 0.86 0.70 0.65 0.59 − 0.39 − 0.02 − 0.16 0.01 0.06 0.04 − 0.13 meters total Train 0.58 0.42 0.52 0.62 0.89 1.00 − 0.45 0.96 0.65 0.55 0.60 − 0.49 − 0.03 − 0.08 − 0.06 0.10 0.06 − 0.11 kilo- meters total Seat kilo- − 0.90 − 0.84 − 0.92 − 0.75 − 0.37 − 0.45 1.00 − 0.36 − 0.67 − 0.75 − 0.60 0.98 − 0.13 − 0.28 0.00 − 0.11 − 0.15 0.27 meters east Train 0.52 0.42 0.49 0.56 0.86 0.96 − 0.36 1.00 0.58 0.53 0.49 − 0.40 − 0.01 − 0.07 − 0.08 0.11 0.06 − 0.05 kilo- meters east Passenger 0.86 0.58 0.75 0.95 0.70 0.65 − 0.67 0.58 1.00 0.83 0.90 − 0.67 − 0.01 − 0.06 0.03 − 0.04 − 0.04 − 0.21 volume Passenger 0.88 0.82 0.89 0.86 0.65 0.55 − 0.75 0.53 0.83 1.00 0.63 − 0.71 0.11 0.13 0.07 0.03 0.04 − 0.22 volume AET Punctuality development and delay explanation factors… 143 1 3 Table 4 (continued) Budget Budget Budget Invest- Seat Train Seat Train Pas- Pas- Freight Freight Depar- Delay Precip- − 10 °C − 15 °C Snow- opera- mainte- O&M ment km km km km senger senger tonnage ton– ture ready itation fall tions nance total total east east volume volume kilom- delay termi- AET eters termi- nal nal Freight 0.73 0.35 0.57 0.80 0.59 0.60 − 0.60 0.49 0.90 0.63 1.00 − 0.57 − 0.06 − 0.13 − 0.01 − 0.07 − 0.07 − 0.24 tonnage Freight − 0.88 − 0.84 − 0.91 − 0.75 − 0.39 − 0.49 0.98 − 0.40 − 0.67 − 0.71 − 0.57 1.00 − 0.12 − 0.26 0.04 − 0.12 − 0.17 0.25 ton-kil- ometers Departure 0.12 0.16 0.15 0.01 − 0.02 − 0.03 − 0.13 − 0.01 − 0.01 0.11 − 0.06 − 0.12 1.00 0.67 0.02 0.01 0.04 0.01 delay termi- nal Delay 0.24 0.25 0.26 0.04 − 0.16 − 0.08 − 0.28 − 0.07 − 0.06 0.13 − 0.13 − 0.26 0.67 1.00 0.09 − 0.07 − 0.03 − 0.06 ready termi- nal Precipita- 0.07 0.03 0.05 0.05 0.01 − 0.06 0.00 − 0.08 0.03 0.07 − 0.01 0.04 0.02 0.09 1.00 − 0.39 − 0.31 − 0.16 tion − 10 °C 0.02 0.14 0.09 − 0.02 0.06 0.10 − 0.11 0.11 − 0.04 0.03 − 0.07 − 0.12 0.01 − 0.07 − 0.39 1.00 0.87 0.39 − 15 °C 0.03 0.19 0.12 0.00 0.04 0.06 − 0.15 0.06 − 0.04 0.04 − 0.07 − 0.17 0.04 − 0.03 − 0.31 0.87 1.00 0.18 Snowfall − 0.24 − 0.23 − 0.25 − 0.24 − 0.13 − 0.11 0.27 − 0.05 − 0.21 − 0.22 − 0.24 0.25 0.01 − 0.06 − 0.16 0.39 0.18 1.00 Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in italic font. Coefficients not significant at the 0.05 level are in regular font 144 A. Økland, N. O. E. Olsson Table  4 presents the correlation between the assumed causes of delays and low punctuality. The assumed causes are treated as independent variables in the subse- quent analyses. However, several of them are not independent of each other. The funds available for operations, maintenance and investment appear to be coupled so that the increase in funding throughout 2010–2014 has resulted in an even increase for each activity. The increased funding has also had a capacity-increasing effect on the network, indicated by a strong correlation between funds and freight ton-kilome- tres and passenger volumes. Weather, constituted by precipitation, snowfall and low temperatures, appears to be independent of all the other assumed causes of low punctuality and delays in the analyses. The same is the case for performance at the freight terminal, as captured by the variables “delay at terminal” and “ready at terminal”. 3.2 C orrelation between assumed causes of delays and low punctuality and the performance of the railway system The following tables present correlation coefficients (Pearson product-moment cor - relation coefficient or Pearson’s r) for the correlation between assumed explanation factors (or drivers of delays and low punctuality) and the performance of the railway system, as expressed by punctuality and/or delay hours. We present the correlation coefficients for the periods 2005–2009 (before the initial study), 2010–2014 (the period after the study as several actions were put in place) and the combined period of 2005–2014 in Tables 5 and 6. Correlation coef- ficients that are significant at the 0.01 level are marked with bold font, those signifi- cant at the 0.05 level are in italic font in the tables. Although not all changes between the periods can be attributed to actions taken from 2010, special note should be taken of factors assumed to be causes of delays and low punctuality of which the direction of the relationship changes (from − to +) or becomes (in-)significant. Table  5 presents the correlation coefficients between delay hours and assumed causes of delays and low punctuality. For the initial period under investigation, there are significant correlations between factors considered to be the responsibility of all the actors (infrastructure manager, passenger and freight operators) and the sum of delays on the railways. Increased infrastructure manager activity, increased number of passengers and increases in freight all coincide with increases in delays. In addi- tion, low temperatures coincided with periods with increased numbers of delays. For the second period (2010–2014), many of these relationships changed or appeared to be dissolved. Infrastructure manager activity increased as delays were reduced, the relationship between the number of train and seat kilometres and delays became insignificant and the number of passengers increased as delays were reduced. The relationship between freight volumes and delays appear to have been reversed or dissolved. The relationship between weather and delays, however, correlates to a higher degree in the second period. The analyses of variance (ANOVA) between weather and punctuality are largely in line with the findings based on correlation. Low temperatures appear to influence overall delay hours and delay hours attributed to the train operating companies in both periods. There is a statistically significant 1 3 Punctuality development and delay explanation factors… 145 1 3 Table 5 Pearson product-moment correlation coefficients (Pearson’s r) between delays and assumed drivers of causes and low punctuality Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Weather Precipitation 0.19 − 0.23 − 0.07 0.28 − 0.05 0.09 0.05 − 0.29 − 0.16 0.19 − 0.18 − 0.03 (> 10 mm) Temperature 0.39 0.62 0.54 0.16 0.19 0.2 0.58 0.77 0.71 0.32 0.46 0.4 (< − 10) Temperature 0.43 0.64 0.57 0.27 0.24 0.26 0.56 0.75 0.68 0.3 0.51 0.42 (< − 15) Snowfall 0.25 0.33 0.1 0.04 0.09 − 0.03 0.38 0.41 0.28 0.34 0.18 0.25 (> 10 cm) IM activ- Funds for 0.68 − 0.47 0.3 0.69 − 0.26 0.29 0.57 − 0.55 − 0.01 0.55 − 0.46 − 0.1 ity operations Funds for 0.68 0.45 0.58 0.71 0.17 0.51 0.56 0.48 0.31 0.51 0.53 0.2 mainte- nance Sum of 0.71 − 0.28 0.46 0.73 − 0.2 0.41 0.59 − 0.36 0.16 0.55 − 0.23 0.05 funds for O&M Investments 0.67 − 0.35 0.22 0.71 − 0.17 0.25 0.54 − 0.46 − 0.08 0.56 − 0.32 − 0.1 146 A. Økland, N. O. E. Olsson 1 3 Table 5 (continued) Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Passenger Seat km total 0.48 − 0.06 0.27 0.43 − 0.01 0.27 0.38 − 0.12 0.08 0.56 0.04 0.19 trans- Seat km 0.27 − 0.06 − 0.38 0.14 − 0.01 − 0.28 0.26 − 0.12 − 0.08 0.43 0.04 0.07 port Oslo Train km 0.14 − 0.09 0.19 0.05 − 0.09 0.13 0.11 − 0.1 0.03 0.35 0.02 0.11 total Train km 0.23 − 0.09 0.21 0.11 − 0.09 0.14 0.22 − 0.1 0.08 0.42 0.02 0.17 Oslo Number of 0.7 − 0.42 0.11 0.72 − 0.16 0.2 0.55 − 0.52 − 0.18 0.65 − 0.41 − 0.18 passengers Number of 0.69 − 0.48 0.41 0.7 − 0.22 0.44 0.55 − 0.57 0.12 0.65 − 0.49 0.09 airport express train trav- ellers Rolling Reduced seat 0.53 0.57 0.49 0.48 0.5 0.44 0.54 0.52 0.52 0.34 0.49 0.44 stock capacity pas- senger trains Punctuality development and delay explanation factors… 147 1 3 Table 5 (continued) Influenc- Indicator Delay hours (sum) Delay hours infrastructure Delay hours all operators Delay hours dispatching ing factor manager 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Freight Tons trans- − 0.21 − 0.45 − 0.04 − 0.19 − 0.17 0.05 − 0.22 − 0.54 − 0.3 − 0.09 − 0.48 − 0.3 opera- ported tion Tons–kilom- 0.41 − 0.27 − 0.36 0.33 − 0.24 − 0.26 0.36 − 0.16 − 0.06 0.51 − 0.4 0.08 eter freight Freight 0.56 0.06 0.19 0.33 0.06 0.15 0.71 0 0.08 0.45 0.13 0.13 rolling ready from terminal Departure 0.63 0.15 0.25 0.55 0.15 0.23 0.61 0.11 0.18 0.55 0.1 0.16 delay terminal Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in italic font. Coefficients not significant at the 0.05 level are in regular font 148 A. Økland, N. O. E. Olsson 1 3 Table 6 Pearson product-moment correlation coefficients (Pearson’s r) between punctuality and assumed causes of delays and low punctuality Influencing Punctuality passenger trains Punctuality regional traffic Punctuality IC Punctuality local traffic Punctuality freight factor 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Weather  Precipitation − 0.18 0.19 0.03 − 0.16 0.16 0.03 − 0.18 − 0.01 − 0.07 − 0.19 − 0.02 − 0.07 − 0.11 0.17 0.05 (> 10 mm)  Temperature − 0.42 − 0.49 − 0.43 − 0.24 − 0.20 − 0.23 − 0.35 − 0.20 − 0.27 − 0.40 − 0.20 − 0.27 − 0.47 − 0.33 − 0.38 (< − 10)  Temperature − 0.45 − 0.56 − 0.45 − 0.23 − 0.26 − 0.27 − 0.46 − 0.30 − 0.34 − 0.43 − 0.30 − 0.34 − 0.38 − 0.30 − 0.31 (< − 15)  Snowfall − 0.34 − 0.24 − 0.30 − 0.13 − 0.11 − 0.02 − 0.26 − 0.10 − 0.09 − 0.36 0.01 − 0.09 − 0.43 − 0.17 − 0.26 (> 10 cm) Infrastructue manager activity  Funds for − 0.45 0.57 0.23 − 0.38 0.27 − 0.22 − 0.52 0.42 − 0.22 − 0.43 0.35 − 0.16 − 0.24 0.55 − 0.03 operations  Funds main- − 0.39 − 0.43 − 0.06 − 0.39 0.00 − 0.35 − 0.48 − 0.25 − 0.43 − 0.33 − 0.27 − 0.34 − 0.14 − 0.36 − 0.23 tenance  Sum of funds − 0.43 0.41 0.09 − 0.41 0.31 − 0.30 − 0.51 0.33 − 0.34 − 0.38 0.24 − 0.26 − 0.18 0.42 − 0.14 O&M  Investments − 0.42 0.46 0.25 − 0.47 0.28 − 0.14 − 0.45 0.37 − 0.12 − 0.34 0.24 − 0.11 − 0.17 0.38 0.02 Passenger transport  Seat km Oslo 0.04 0.24 0.20 0.26 0.28 0.09 0.03 0.33 0.03 − 0.17 0.24 − 0.03 0.02 0.10 − 0.02  Train km − 0.06 0.20 − 0.14 0.11 0.25 0.28 − 0.01 0.27 0.30 − 0.23 0.12 0.24 − 0.05 − 0.01 0.16 total  Train km 0.00 0.24 0.17 0.21 0.28 0.10 0.01 0.33 0.02 − 0.21 0.24 − 0.06 − 0.03 0.10 − 0.04 Oslo  Number of − 0.52 0.49 0.29 − 0.53 0.21 − 0.13 − 0.49 0.37 − 0.06 − 0.45 0.25 − 0.06 − 0.28 0.37 0.05 passengers  Number of − 0.53 0.56 0.04 − 0.56 0.25 − 0.34 − 0.45 0.42 − 0.29 − 0.47 0.34 − 0.24 − 0.33 0.47 − 0.14 passengers AET Punctuality development and delay explanation factors… 149 1 3 Table 6 (continued) Influencing Punctuality passenger trains Punctuality regional traffic Punctuality IC Punctuality local traffic Punctuality freight factor 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005– 2005– 2010– 2005–2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 2014 2009 2014 Rolling stock passenger trains  Reduced seat − 0.48 − 0.64 − 0.58 − 0.44 − 0.58 − 0.49 − 0.54 − 0.56 − 0.51 − 0.36 − 0.53 − 0.45 − 0.25 − 0.36 − 0.30 capacity Freight operation  Tons trans- 0.05 0.50 0.36 0.08 0.19 − 0.04 0.07 0.38 0.03 0.02 0.30 0.03 − 0.06 0.38 0.08 ported  Ton kilom- − 0.34 0.23 − 0.17 − 0.30 0.10 0.24 − 0.22 0.14 0.28 − 0.44 0.42 0.24 − 0.42 0.39 0.12 eter freight  Departure − 0.58 − 0.05 − 0.11 − 0.47 − 0.14 − 0.21 − 0.60 0.02 − 0.11 − 0.52 − 0.05 − 0.14 − 0.49 − 0.10 − 0.17 delay terminal Correlation is significant at the 0.01 level for factors in bold font (two-tailed) and at the 0.05 level (two-tailed) for factors in regular font. Coefficients not significant at the 0.05 level are marked with a strikethrough line Year-by-year allocations from the National Budget Numbers from NSB AS, the former national train operator (now Vy) 150 A. Økland, N. O. E. Olsson relationship between snowfall and delay hours attributed to dispatching for both periods. Delay hours attributed to the infrastructure manager follow a similar pattern. Spe- cial note should be taken of the strong degree of correlation between infrastructure manager activities in the period 2005–2009. In the subsequent period of 2010–2014, the correlation is no longer significant. Delay hours attributed to the Infrastructure Manager in the second period appear to be largely independent of all the assumed causes of delays and low punctuality, the only exceptions being reduced train length (which is a factor under the train operators’ control) and funds for operations (which correlates negatively with IM delay hours in the second period, hence increased funding indicates a reduced number of delay hours). Delay hours attributed to the passenger train operating companies correlate closer with weather in the second period than in the initial period. Production volume (seat and train kilometres) and the number of passengers correlate less closely in the sec- ond period, where the correlation is largely insignificant. The correlation between incidents of reduced train length and delay hours attributed to passenger train opera- tors remain approximately unchanged from the initial to the second period. Similarly, delay hours attributed to dispatching correlate more closely with the weather in the second period compared to the initial period. Production volume (seat and train kilometres) and the number of travellers correlate closely with delay hours attributed to dispatching in the initial period. In the second period, the relation- ship appears to be insignificant. As was the case with delay hours attributed to the infrastructure manager and the passenger train operators, incidents of reduced train length correlate with delay hours in the second period. The relationship between freight train volumes and performance at the terminals is reversed or dissolved in the second period. Table  6 presents the Pearson correlation factors between assumed causes of delays and low punctuality and punctuality of different types of train traffic. The causes of low punctuality are expected to contribute to a lowering in the percentage of trains that reach their destination on time, so the correlation coefficients are nega- tive when the relationship is as expected. The correlation coefficients of the assumed causes of low punctuality and punc- tuality are for most of the cases in the region of −  0.4 for the 2005–2009 period. The exceptions are production volumes (seat and passenger train kilometers and tons transported) and precipitation, all of which are close to zero and not significant. The correlation between bad weather and low punctuality is lower for the sec- ond period for local passenger traffic and freight. For overall punctuality and bad weather, the correlation coefficients are higher in the second period with strong snowfall as the only exception. The correlation between assumed causes of delays and low punctuality and over- all punctuality changes very little between the two periods in the investigation. Punc- tuality for regional traffic, on the other hand, oversees a reduction in factors with a significant correlation from eight in the initial period to a single significant variable in the second period. The reduction in variables that correlates at the 0.01-level with punctuality for local traffic is similarly reduced from 12 in the initial period to one in 1 3 Punctuality development and delay explanation factors… 151 the second period (three variables have correlation coefficients that are significant at the 0.01-level in both periods, but the signs have changed). There were several instances of reversed relationships between the assumed causes of low punctuality and punctuality for freight trains from the initial to the second period in the investigation. 3.3 Regression models of delays and punctuality Following the pairwise correlations, we present the regression models in which the identified factors’ relationship with the number of delay hours produced by the system is proposed. To propose quantifications of the relationship between the assumed causes and delays, regression models were developed using regu- lar least-square models and the GRETL software (GNU Regression, Econometric and Time-series Library). The regression coefficients have been standardized in Tables  7 and 8. Standardization of the coefficients is performed to facilitate the evaluation of the effect of each independent variable on the dependent variable. The initial calculations of the correlation coefficients for punctuality, delays and their assumed causes were presented during discussions of the task force to identify root causes and primary mechanisms explaining how the assumed causes actually influenced the railway system (and which actors were vulnerable for the various assumed causes). These are discussed further in Sect.  4. However, these discussions formed the basis for the reduced set of assumed causes of delays and low punctuality included in the regression models. Cold winter weather (represented by the indicators “number of days with less than 10  °C”, “number of days with less than 15  °C” and “number of days with more than 10 cm snowfall” and number of days with more than 10 mm precipita- tion) was identified as essential to all actors. However, although some weather- factors are significant at the 0.05-level in every model (except delays due to dis- patching 2010–2014), weather is not the dominant cause of delays at the “per month” level. The passenger operating company acknowledged that splitting up trains to use shorter trains than planned produced delays in the system and contributed to delays attributed to other actors. This finding is supported by the regression models. The variable “Reduced train length” is significant in every model except for delay hours attributed to dispatching for 2005–2009. The regression model for the sum of delay hours could be represented well by the reduced set of independent variables (R of 0.83 and 0.79). The only variable that was significant at the 0.05-level for both periods was reduced train length. Funds for investment contributed to fewer delay hours in the second period, whereas funds for operation and management contribute to delays in the model. Freight volumes (ton kilometer) and departure delays at terminal changed from being significant at the 0.01 and 0.05-level to becoming insignificant. The regression model of delay hours attributed to the Infrastructure Manager by the identical set of independent variables resulted in a good fit for the initial period 1 3 152 A. Økland, N. O. E. Olsson 1 3 Table 7 Regression models of delay hours Delay hours (sum) IM TOCs Dispatching 2005–2009 2090–2014 2005–2009 2010–2014 2005–2009 2010–2014 2005–2009 2010–2014 Constant − 5.23*** − 14.05*** − 2.85 − 9.71 − 5.28*** − 11.15*** − 8.05*** − 15.56*** Weather  Precipitation > 10 mm 0.17** − 0.12 0.21** − 0.22 0.09 − 0.03 0.16* − 0.06  Temperature < − 10 °C 0.14 0.14 − 0.09 − 0.26 0.38** 0.42*** 0.06 − 0.11  Temperature < − 15 °C 0.18 0.19 0.25 0.12 0.11 0.15 0.07 0.28  Snowfall > 10 cm 0.07 0.19** − 0.02 0.15 0.05 0.13* 0.27*** 0.15 Infrastructure manager activity  Funds for operations and maintenance 0.19 0.85*** 0.17 0.34 0.23 0.75*** 0.02 1.15***  Investment 0.24* − 1.17*** 0.30* − 0.54* 0.08 − 1.14*** 0.31* − 1.56*** Passenger transport  Train kilometers − 0.03 − 0.94*** − 0.15 − 1.54*** 0.00 − 0.40 0.22* − 0.14  Seat kilometers 0.09 1.45*** 0.17 2.11*** 0.03 0.73** 0.01 0.69* Rolling stock passenger trains  Reduced seat capacity 0.20** 0.51*** 0.17* 0.71*** 0.23*** 0.27*** 0.12 0.41*** Freight operation  Freight ton–kilometers 0.27*** − 0.09 0.14 0.25 0.31*** − 0.17* 0.35*** − 0.47***  Average departure delay from terminal 0.16** 0.06 0.16 0.11 0.12 0.02 0.17* − 0.02 R of model 0.83 0.79 0.73 0.46 0.81 0.87 0.75 0.77 Variables statistically significant at the 0.01-level are marked by a triple asterisk (***), variables statistically significant at the 0.05-level are marked by a double asterisk (**) and variables statistically significant at the 0.1-level are marked by a simple asterisk (*) Punctuality development and delay explanation factors… 153 1 3 Table 8 Regression models for punctuality Punctuality commuter trains Punctuality all passenger trains Punctuality freight trains 2005–2009 2010–2014 2005–2009 2010–2014 2005–2009 2010–2014 Constant 29.27*** 13.04** 27.98*** 34.14*** 15.61*** 12.77** Weather  Precipitation > 10 mm − 0.20* − 0.01 − 0.23** 0.13 − 0.16 0.12  Temperature < − 10 °C 0.00 0.15 − 0.08 0.16 − 0.29 − 0.33  Temperature < − 15 °C − 0.29 − 0.17 − 0.22 − 0.33 − 0.02 0.32  Snowfall > 10 cm − 0.22* − 0.08 − 0.18 − 0.18* − 0.24* − 0.14 Infrastructure manager activity  Funds for operations and maintenance − 0.04 − 0.49** 0.25 − 0.58*** 0.10 − 0.34  Investment − 0.05 0.78*** − 0.30 1.00*** − 0.07 1.08*** Passenger transport  Train kilometers − 0.06 1.10** 0.25* 0.95** 0.10 1.80***  Seat kilometers − 0.02 − 1.27** − 0.23 − 1.30*** 0.04 − 2.30*** Rolling stock passenger trains  Reduced seat capacity − 0.19 − 0.43*** − 0.24** − 0.52*** − 0.07 − 0.24* Freight operation  Freight ton-kilometers − 0.38*** 0.31 − 0.19* 0.07 − 0.40*** 0.14  Average departure delay from terminal − 0.15 0.06 − 0.26** 0.07 − 0.24* 0.01 R of model 0.60 0.55 0.66 0.70 0.56 0.66 Variables statistically significant at the 0.01-level are marked by a triple asterisk (***), variables statistically significant at the 0.05-level are marked by a double asterisk (**) and variables statistically significant at the 0.1-level are marked by a simple asterisk (*) 154 A. Økland, N. O. E. Olsson of investigation (R of 0.73). The fit between modelled and actual delay hours for the second period was significantly lower (R of 0.46). The fit between actual and modelled delay hours attributed to the passenger train operating companies was very close (R of 0.81 and 0.87). Low temperatures (num- ber of days colder than −  15  °C) was significant at the 0.05-level in both periods. The regression model for delay hours attributed to dispatching was the only one in which all assumed causes of delays and low punctuality were represented with posi- tive coefficients. Half of these signs changed in the second period. The fit of the regression models for punctuality was lower than those of the mod- els of delay hours. This is to be expected as trains may catch up to their timetable after being delayed. Three models are presented: punctuality for commuter trains, average punctuality for all passenger trains and punctuality for freight trains. The three models are quite similar with regards to significant variables and development from the initial to the second period. Weather is not presented as the main cause of low punctuality in the models. However, snowfall is significant at the 0.1-level in three models. Funds for invest- ment and funds for operations and management are significant in the second period for all three models. The same is the case for the production volume of passenger train services. Freight volumes are presented as a cause of low punctuality in the initial period of the study. However, in the latter period, the variable becomes either insignificant or appears as a factor contributing to high punctuality. 4 Discussion The original study indicated that development in delay hours in 2005–2009 was due to a combination of three factors: (1) an increased error rate in infrastructure and rolling stock, (2) extensive work close to the tracks due to new investments and an increased amount of maintenance and (3) an inability to address normal varia- tions of weather conditions. The study highlighted that the Norwegian railway had a systematic winter issue. Delays occurred to a greater extent in years with colder winters, compared to years with milder winters. In addition, construction work and activity on the tracks were related to increased delays. When construction activities increased, so did the delay hours. The increase in delay hours and lowering punctuality from 2005–2009 appeared as a year-on-year trend, with the winter of 2009/2010 at the extreme end. It was, therefore, to some extent expected that the railway’s performance would “regress to the mean” in the years following 2010. As was generally expected after record-lev- els of delays in 2009 and 2010, the following years proved to be better with regard to delays especially from 2012, as shown in Fig. 1. In the years following the investigation, a range of measures was adopted by both IM and the TOCs. These measures include extra capacity (manpower) for the removal of snow at strategically important parts of the infrastructure (especially switches), and electric heating of switches was gradually put in place. Conduc- tor rails have been installed in the Oslo tunnel to reduce the incidence of damage 1 3 Punctuality development and delay explanation factors… 155 to overhead power lines. New rolling stock was put in operation (introduced from December 2012) to serve local and regional traffic in the greater Oslo region. Addi- tionally, a new timetable was put in place in December 2013. Publicity campaigns in the form of posters at the stations and on the platforms were produced to change traveler behavior regarding how to board and alight from the train. Markings were made on the platforms to facilitate positioning for the travelers preparing to board the train, as well as making it easier for the train drivers to stop at the appropriate place at the platform. Five years later, some of the measures taken are perceived as being highly suc- cessful, whereas the measures that were expected to have the greatest effect have yet to produce extensive results. The effects of the measures taken can be evaluated by analysing data for the period 2010–2014 by extending the time series and reviewing the correlation and regression series. In the following sections, we discuss in more detail the extent and the mecha- nisms of how the assumed causes of delays and low punctuality affect the rail system to produce delays. This analysis can be used as an ex post analysis of the effects of implemented measures, and especially the combined effects and their influence on the whole railway system. The regression models are suitable to identify how rela- tionships between assumed causes and the assumed resulting low punctuality and delays have changed. The measures that have been put in place vary with regards to when and how gradually they have been introduced. Some, such as the introduction of a new timetable, are in operation from a fixed date. Others, such as the introduc- tion of new rolling stock, have been gradually introduced over several years. 4.1 Winter—variations in weather The various seasons each introduce distinct challenges for rail operations, such as frost heaving in early spring, sun kink during summer, and defoliation dur- ing autumn. Figure  1 reveals that the Norwegian railway has systematic winter issues.  Every year sees a dip in punctuality during winter and an increase in both delay hours and the number of cancellations. One may expect trouble to occur in periods with especially severe weather, as is the case with other modes of trans- portation. It appears, however, that it is not only the “extreme” weather that causes problems for Norwegian railways but also regular winter. Only winters that are exceptionally mild have seen rail operations performing in line with the norm for the rest of the year. The regression models only partially support the notion that weather is an impor- tant cause of delays and low punctuality. There may be several explanations as to why that is. One is the resolution in the analyses. Instances of “bad” or extreme weather rarely last for months. Still, every model (with two exceptions for the sec- ond period) includes at least one weather-variable that is significant at the 0.01-level. There were two distinct issues with winter operations that concerned the repre- sentatives from the IM and TOCs. One was the failure rate of switches and cross- ings, which increased due to ice forming and obstructing them from locking in posi- tion. The second was snow on the rolling stock melting when trains passed through 1 3 156 A. Økland, N. O. E. Olsson tunnels, to re-freeze once the trains left the tunnels. Both were of special impor- tance in the Oslo area. There has been an increase in the rate of introducing electric heating to switches and crossings after 2010. The number of tunnels, on the other hand, is also increasing because new railway lines in densely populated areas tend to require lines to run underground. The study indicates that the snow has a stronger impact on the punctuality at the final destination than on the number of delay hours, whereas low temperature is more important for delays. The correlations between snowfall and low temperature on the one side and goods freight and passenger traffic on the other were similar in magnitude, implying that freight and passenger traffic are somewhat equally influ- enced by winter conditions. 4.2 Infr astructure manager activity The investigation focused on infrastructure manager activity rather than instances of infrastructure failures. Infrastructure failures (and partial failures) may result in temporary speed restrictions, a full stop of all traffic or no effect at all on traffic. Old infrastructure is usually more prone to failures than new (after the initial run-in period). When failures occur, identifying, getting to and locating the failure sources often take more time than the repairs. However, the data on infrastructure condition and the number of failures were not significant when introduced in the regression model for 2005–2009. The corresponding data for 2010–2014 was not evaluated in the ex post investigation. Infrastructure failures are probably still relevant, for exam- ple, as part of the mechanism in which the weather influenced the number of delay hours. Instead, a hypothesis was put forward that increased infrastructure manager activ- ity, with the aim of reducing the number of delays and increase capacity on the net- work through operations, maintenance activities, investment projects, and upgrades, which were a cause for delays and low punctuality. The study documented the unfortunate link between action to reduce delays and the amount of delays in the railway system for the period 2005–2009. Maintenance activities and investment in upgrading infrastructure, as well as the construction of new infrastructure, contributed significantly to delays in the period up to 2009. The amount of IM operation and maintenance and construction work increased rather than decreased in the years following 2010. Still, both the correlation and regres- sion models indicated a reversal in the relationship between investment and delays and low punctuality for the second period. This raises questions regarding the causal relationship between construction (investment), operations and maintenance and delays and low punctuality. The causal relationships are multi-faceted and are expected to include: 1. Low punctuality. This highlights the need for increased maintenance and invest- ments in the infrastructure (indicating that funds for construction and maintenance lag the development in punctuality). 1 3 Punctuality development and delay explanation factors… 157 2. Ongoing work (both construction and maintenance). This affects traffic due to the introduction of speed restrictions and capacity limitations as work is conducted. The effect will increase in cases where the timetable is not adjusted according to current capacity/speed limits. 3. Punctuality levels. These increase after work has been performed, but mainly after a run-in period for new infrastructure and after new times are introduced, as shown by Olsson (2006). During construction close to infrastructure in operation, as well as some main- tenance work, temporary speed restrictions are put in place. Speed restrictions increase travel time, reduce capacity and remove buffers on the network. From 2010, additional care has been taken to ensure sufficient buffers in the timetables for lines where investment projects were expected to take place. Additional measures to avoid investment, operations and maintenance resulting in delays and low punctuality include executing these in periods with less traffic (summer, nights and weekends). Even with these measures in mind though, it should not be expected that invest- ments actually work as buffers against delays; some elements of chance or some confounding factors are more probably in play. 4.3 Passenger transport and rolling stock Reduced seat capacity showed a strong correlation (between 0.49 and 0.66) with the total number of delay hours, delay hours attributed to the main passenger train operator and delay hours attributed to dispatching. Reduced seat capacity due to shorter trains was only studied for passenger trains. Splitting of double sets would often result in a reduced number of seats and available doors to board and step off the train, and hence the need for longer stops at stations. In addition to reduced seat capacity, shorter trains may also mean that passengers standing along the full plat- form length may need to walk along the platform to board. The total number of pas- senger train kilometers was also identified as being correlated with the number of delay hours attributed to the IM. In the regression models presented in Tables  7 and 8, a reduced train length (compared with the planned number) resulted in an increased number of delay hours attributed to the infrastructure manager as well as to the operator for both passenger and freight trains. This result was expected for passenger trains but not for freight trains and caused a debate in the task force. Periods in which there were less split- tings of trains also saw reductions in the number of delay hours attributed to the infrastructure manager, which may indicate that splitting trains is a way of reduc- ing the inconvenience of passengers when severe delays have occurred and rolling stock is not in a position to execute the timetable as planned, independent of who is responsible for the initial delays. 1 3 158 A. Økland, N. O. E. Olsson 4.4 Freight The total ton-kilometers (the product of tons of goods and the number of kilometers it was transported) was identified as significant for overall delay hours as well as for passenger operators’ and goods freight operators’ delay hours. The regression models support the notion of freight ton-kilometers as a factor contributing to delays and low punctuality only in the initial period. In the second period, the relationship appeared to be reversed, with the exception of delay hours attributed to the infra- structure manager. Freight trains do not disturb regular traffic as long as they keep up with their schedule. If they do not, the single-tracks of the Norwegian railway system result in delays, with the risk of spreading to the rest of the network. Freight train punctuality effectively illustrates the vulnerability of the rail system. Departure punctuality from the freight terminal has, therefore, traditionally been treated as an essential issue. Departure punctuality is closely related to “freight train ready at terminal”, which is logged by the freight operator. Sufficient turnaround times, available personnel and lift capacity are key factors to address for the opera- tors to ensure punctual departure. However, the variables “ready at terminal” and “average departure delay from terminal” are significant in a lower number of the regression models than might have been expected. A possible explanation lies in the nature of using averages. Higher resolution for the data (for instance average depar- ture delay and delay hours per day) will probably provide additional insight into the relationship between departure delays and performance on the rail network. 5 Conclusion The paper has documented a revisit of an investigation into causes of delays and low punctuality in the Norwegian train system. Enabled by new data on performance in the years following the initial analysis, new analyses provide the grounds for re-eval- uating the original findings. Appending data for 2010–2014, new regression models indicate that although their influence on delays and low punctuality has changed as various measures have been put in place, the same factors remain influential: low temperature (< − 10 °C and < − 5 °C) and snowfall (> 10 cm), reduced train lengths (mainly due to running single rather than double sets of rolling stock) and increased volume of train services (freight and passenger trains) still contribute to delays and low punctuality. The relationship between infrastructure management activity (oper- ations, maintenance and investment) and delays and punctuality has been reversed in the models for the second period. In the first period, more activity was correlated with more delays, while this was not the case in the second period. The scientific contribution of this paper is related to two aspects. First, we con- tribute to the literature on empirical analyses of delay causes. Second, we illus- trate an approach for ex post evaluation of effects from punctuality improvement initiatives. 1 3 Punctuality development and delay explanation factors… 159 Acknowledgements Open Access funding provided by NTNU Norwegian University of Science and Technology (incl St. Olavs Hospital - Trondheim University Hospital). The authors would like to thank everyone who contributed to the analyses from Jernbaneverket, NSB, CargoNet and Flytoget (the Airport Express Train). Open Access This article is licensed under a Creative Commons Attribution 4.0 International License, which permits use, sharing, adaptation, distribution and reproduction in any medium or format, as long as you give appropriate credit to the original author(s) and the source, provide a link to the Creative Com- mons licence, and indicate if changes were made. The images or other third party material in this article are included in the article’s Creative Commons licence, unless indicated otherwise in a credit line to the material. If material is not included in the article’s Creative Commons licence and your intended use is not permitted by statutory regulation or exceeds the permitted use, you will need to obtain permission directly from the copyright holder. To view a copy of this licence, visit http://creat iveco mmons .org/licen ses/by/4.0/. References Andersson E (2014) An economic evaluation of the swedish prioritisation rule for conflict resolution in train traffic management. Proc Soc Behav Sci 111:634–644. https ://doi.org/10.1016/j.sbspr o.2014.01.097 Andersson EV, Peterson A, Törnquist Krasemann J (2013) Quantifying railway timetable robustness in critical points. J Rail Transp Plan Manag 3(3):95–110. https ://doi.org/10.1016/j.jrtpm .2013.12.002 Bender M, Büttner S, Krumke S (2013) Online delay management on a single train line: beyond competi- tive analysis. Plan Oper 5(3):243–266. https ://doi.org/10.1007/s1246 9-013-0070-z Benezech V, Coulombel N (2013) The value of service reliability. Transp Res Part B 58(C):1–15. https :// doi.org/10.1016/j.trb.2013.09.009 Bergström A, Krüger N (2013) Modeling passenger train delay distributions—evidence and implications. IDEAS Working Paper Series from RePEc Carey M, Carville S (2003) Scheduling and platforming trains at busy complex stations. Transp Res Part A: Policy Pract 37(3):195–224. https ://doi.org/10.1016/S0965 -8564(02)00012 -5 Coulombel N, De Palma A (2014) Variability of travel time, congestion, and the cost of travel. Math Popul Stud: Risky Time Prospects Travel Demand 21(4):220–242. https ://doi.org/10.1080/08898 480.2013.83642 0 Enno Wiebe L (2010) Factsheet snow and ice. Retrieved April 21, 2011, from UIC Information Platform “Winter and Railways” Gibson S, Cooper G, Ball B (2002) The evolution of capacity charges on the UK rail network. J Transp Econ Policy 36(2):341–354 Gorman MF (2009) Statistical estimation of railroad congestion delay. Transp Res Part E: Logist Transp Rev 45(3):446–456. https ://doi.org/10.1016/j.tre.2008.08.004 Hadiuzzaman M, Malik DMG, Barua S, Qiu TZ, Kim A (2019) Modeling passengers’ perceptions of intercity train service quality for regular and special days. Public Transp 11(3):549–576. https ://doi. org/10.1007/s1246 9-019-00213 -0 Hansen IA, Pachl J (2008) Railway timetable and traffic: analysis. Modelling, Simulation, Eurailpress, Hamburg Harris NG, Godward EW (1992) Planning passenger railways: A handbook. Derbyshire Transport Publish- ing Company Limited, Glossop Harris NG, Mjøsund CS, Haugland H (2013) Improving railway performance in Norway. J Rail Transp Plan Manag 3(4):172–180. https ://doi.org/10.1016/j.jrtpm .2014.02.002 Heinz W (2003) Passenger service times on trains. KTH Royal Institute of Technology, Stockohlm Huang Y, Dong Y, Zhao Y-K (2011) Simulation study of temporary speed restriction on train operation. J Railw Signal Commun 47(1):13–15 Jernbaneverket (2015) Jernbanestatistikk 2015. https ://www.jernb anedi rekto ratet .no/globa lasse ts/docum enter /jernb aneve rket-stati stikk -2015.pdf. Accessed 19 May 2020 König E (2020) A review on railway delay management. Public Transp. https ://doi.org/10.1007/s1246 9-020- 00233 -1 1 3 160 A. Økland, N. O. E. Olsson Kristoffersson I, Pyddoke R (2019) A traveller perspective on railway punctuality: passenger loads and punc- tuality for regional trains in Sweden. Paper presented at the RailNorrköping 2019. 8th international conference on railway operations modelling and analysis (ICROMA), Norrköping, Sweden, June 17th– 20th, 2019 Kroes E, Kouwenhoven M, Duchateau H, Debrincat L, Goldberg J, Kroes E (2007) Value of punctuality on suburban trains to and from Paris. Transp Res Rec 2006:67–75. https ://doi.org/10.3141/2006-08 Lam TC, Small KA (2001) The value of time and reliability: measurement from a value pricing experiment. Transp Res Part E 37(2):231–251. https ://doi.org/10.1016/S1366 -5545(00)00016 -8 Li Z, Hensher DA, Rose JM (2010) Willingness to pay for travel time reliability in passenger transport: a review and some new empirical evidence. Transp Res Part E 46(3):384–403. https ://doi.org/10.1016/j. tre.2009.12.005 Liu H, Lu H, Lu M, Zhang J (2009) Study on the system design and optimal models of urban rail transit traction calculation system. In: ICCTP 2009: critical issues in transportation systems planning, develop- ment, and management, pp 1–7) Ludvigsen J, Klæboe R (2014) Extreme weather impacts on freight railways in Europe. Nat Hazards 70(1):767–787. https ://doi.org/10.1007/s1106 9-013-0851-3 Monchambert G, de Palma A (2014) Public transport reliability and commuter strategy. J Urban Econ 81(1):14–29. https ://doi.org/10.1016/j.jue.2014.02.001 Noland RB, Polak JB (2002) Travel time variability: a review of theoretical and empirical issues. Transp Rev 22(1):39–54. https ://doi.org/10.1080/01441 64001 00224 56 Norheim B, Ruud A (2011) The underestimated demand for public transport? Paper presented at the Euro- pean transport conference 2011 association for European transport (AET) transportation research board Nyström B (2008) Aspects of improving punctuality: from data to decision in railway maintenance. PhD thesis. Luleå University of Technology Olsson NOE, Haugland H (2004) Influencing factors on train punctuality—results from some Norwegian studies. Transp Policy 11(4):387–397. https ://doi.org/10.1016/j.tranp ol.2004.07.001 Olsson N, Økland A, Veiseth M, Stokland Ø (2010) Driftsstabilitet på Jernbaneverkets nett—årsaksanalyser 2005–2010. Punktlighets- og regularitetsutviklingen, gransking av årsaker. SINTEF, Trondheim Palmqvist C-W (2019) Delays and timetabling for passenger trains, vol 317. PhD thesis. Lund University, Lund Palmqvist C-W, Tomii N (2019) Overtakes and dwell time delays for Japanese commuter trains. In: 15th world conference on transportation research, Mumbai, India Palmqvist C-W, Olsson N, Hiselius L (2017) Delays for passenger trains on a regional railway line in South- ern Sweden. Int J Transp Dev Integr 1(3):421–431. https ://doi.org/10.2495/TDI-V1-N3-421-431 Palmqvist C-W, Tomii N, Ochiai Y (2020) Explaining dwell time delays with passenger counts for some commuter trains in Stockholm and Tokyo. J Rail Transp Plan Manag. https ://doi.org/10.1016/j.jrtpm .2020.10018 9 (in press, corrected proof) Parbo J, Nielsen OA, Prato CG (2016) Passenger perspectives in railway timetabling: a literature review. Transp Rev 36(4):500–526. https ://doi.org/10.1080/01441 647.2015.11135 74 Paulley N, Balcombe R, Mackett R, Titheridge H, Preston J, Wardman M, White P (2006) The demand for public transport: the effects of fares, quality of service, income and car ownership. Transp Policy 13(4):295–306. https ://doi.org/10.1016/j.tranp ol.2005.12.004 Rietveld P, Bruinsma FR, van Vuuren DJ (2001) Coping with unreliability in public transport chains: a case study for Netherlands. Transp Res Part A 35(6):539–559. https ://doi.org/10.1016/S0965 -8564(00)00006 -9 Salkonen R, Paavilainen J (2010) Measuring railway traffic punctuality from the passenger’s perspective. Paper presented at the general proceedings of the 12th world conference on transport research (WCTR), Lisbon, Portugal, July 11–15, 2010 Seco A, Gonçalves J (2007) The quality of public transport: relative importance of different performance indicators and their potential to explain modal choice. Urban transport XIII: urban transport and the environment in the 21st century, pp 313–325 Sørensen AØ, Bjelland J, Bull-Berg H, Landmark AD, Akhtar MM, Olsson NOE (2018) Use of mobile phone data for analysis of number of train travellers. J Rail Transp Plan Manag 8(2):123–144. https :// doi.org/10.1016/j.jrtpm .2018.06.002 Szafránski Z (2011) Winter and railways-study. Retrieved from UIC website: http://www.uic.org/forms /IMG/ pdf/500_uic_siafi _repor t__winte r_and_railw ays.pdf Takeuchi Y, Tomii N, Hirai C (2007) Evaluation method of robustness for train schedules. Q Rep RTRI 48(4):197–201. https ://doi.org/10.2219/rtriq r.48.197 1 3 Punctuality development and delay explanation factors… 161 Tomii N (2010) How the punctuality of the Shinkansen has been achieved. WIT Trans Built Environ 114:111–120. https ://doi.org/10.2495/CR100 111 Trafikverket (2010) Utredning Järnväg Vinter. Situationen för järnvägen under vintern 2009/10—Trafikver - ket, Borlänge van Hagen M, Sauren J (2014) Influencing the train experience: using a successful measurement instrument, vol 1, pp 264–275 Vromans M (2005) Reliability of railway systems. Erasmus University, Rotterdam Wallander J, Mäkitalo M (2012) Data mining in rail transport delay chain analysis. Int J Shipp Transp Logist 4(3):269–285. https ://doi.org/10.1504/IJSTL .2012.04749 2 Wang P, Zhang Q-P (2019) Train delay analysis and prediction based on big data fusion. Transp Saf Environ 1(1):79–88. https ://doi.org/10.1093/tse/tdy00 1 Wardman M (2001) A review of British evidence on time and service quality valuations. Transp Res Part E 37(2):107–128. https ://doi.org/10.1016/S1366 -5545(00)00012 -0 Wenyi J, Xin C, Zhangdui Z (2010) The impact of quality of services in chinese train control system on train delays analysis. In: 2010 IEEE 72nd vehicular technology conference—fall, September 2010, pp 1–5 Xia Y, Van Ommeren JN, Rietveld P, Verhagen W (2013) Railway infrastructure disturbances and train operator performance: the role of weather. Transp Res Part D: Transp Environ 18:97–102. https ://doi. org/10.1016/j.trd.2012.09.008 Zakeri G, Olsson NOE (2017) Investigation of punctuality of local trains—the case of Oslo area. Transp Res Proc 27:373–379. https ://doi.org/10.1016/j.trpro .2017.12.080 Zhou Y, Mi C (2013) Modeling and simulation of train movements under scheduling and control for a fixed-block railway network using cellular automata. Simulation 89(6):771–783. https ://doi. org/10.1177/00375 49713 48740 3 Publisher’s Note Springer Nature remains neutral with regard to jurisdictional claims in published maps and institutional affiliations. 1 3