Get 20M+ Full-Text Papers For Less Than $1.50/day. Start a 14-Day Trial for You or Your Team.

Learn More →

Amec Civil Engineering Ltd v Secretary of State for Transport

Amec Civil Engineering Ltd v Secretary of State for Transport 11 October 2004 Jackson, J Technology and Construction Court [2004] EWHC 2339 [2004] ArbLR 2 Arbitration award--Challenge--Jurisdiction--Reference to arbitration-- Preconditions--Validity of Engineer's decision--Existence of `dispute'-- Short time limit imposed to consider claim--Whether `dispute' arising for reference to Engineer (yes)--Whether Engineer subject to rules of natural justice (no)--Whether Engineer's decision invalidated by conflict of interest (no)--Whether arbitrator's jurisdiction limited to defects identified by Engineer (no)--Whether arbitrator has jurisdiction over all matters referred to Engineer (yes)--Arbitration Act 1996, s 67 Engineer's decision valid precondition to arbitration despite conflict of interest and failure to apply rules of natural justice The Secretary of State entered into a contract with Amec Civil Engineering Ltd for renovation works at Thelwall Viaduct. The contract was on the ICE conditions (5th edn). The works were substantially completed in 1996. Defects came to light in 2002. The Highways Agency referred the matter to the Engineer under the contract, but also made a parallel claim against the Engineer. Amec's correspondence was not made available to the Engineer, nor was Amec afforded an opportunity to make submissions. The decision was requested urgently and the Engineer drafted it before receiving the formal request which was not copied to Amec. The http://www.deepdyve.com/assets/images/DeepDyve-Logo-lg.png Arbitration Law Reports and Review Oxford University Press

Amec Civil Engineering Ltd v Secretary of State for Transport

Arbitration Law Reports and Review , Volume 2004 (1) – Jan 1, 2004

Amec Civil Engineering Ltd v Secretary of State for Transport

Arbitration Law Reports and Review , Volume 2004 (1) – Jan 1, 2004

Abstract

11 October 2004 Jackson, J Technology and Construction Court [2004] EWHC 2339 [2004] ArbLR 2 Arbitration award--Challenge--Jurisdiction--Reference to arbitration-- Preconditions--Validity of Engineer's decision--Existence of `dispute'-- Short time limit imposed to consider claim--Whether `dispute' arising for reference to Engineer (yes)--Whether Engineer subject to rules of natural justice (no)--Whether Engineer's decision invalidated by conflict of interest (no)--Whether arbitrator's jurisdiction limited to defects identified by Engineer (no)--Whether arbitrator has jurisdiction over all matters referred to Engineer (yes)--Arbitration Act 1996, s 67 Engineer's decision valid precondition to arbitration despite conflict of interest and failure to apply rules of natural justice The Secretary of State entered into a contract with Amec Civil Engineering Ltd for renovation works at Thelwall Viaduct. The contract was on the ICE conditions (5th edn). The works were substantially completed in 1996. Defects came to light in 2002. The Highways Agency referred the matter to the Engineer under the contract, but also made a parallel claim against the Engineer. Amec's correspondence was not made available to the Engineer, nor was Amec afforded an opportunity to make submissions. The decision was requested urgently and the Engineer drafted it before receiving the formal request which was not copied to Amec. The

Loading next page...
 
/lp/oxford-university-press/amec-civil-engineering-ltd-v-secretary-of-state-for-transport-2be3JPsuem

References (0)

References for this paper are not available at this time. We will be adding them shortly, thank you for your patience.

Publisher
Oxford University Press
Copyright
© Oxford University Press, 2007
Subject
Judgments
ISSN
2044-8651
eISSN
2044-9887
DOI
10.1093/alrr/2004.1.13
Publisher site
See Article on Publisher Site

Abstract

11 October 2004 Jackson, J Technology and Construction Court [2004] EWHC 2339 [2004] ArbLR 2 Arbitration award--Challenge--Jurisdiction--Reference to arbitration-- Preconditions--Validity of Engineer's decision--Existence of `dispute'-- Short time limit imposed to consider claim--Whether `dispute' arising for reference to Engineer (yes)--Whether Engineer subject to rules of natural justice (no)--Whether Engineer's decision invalidated by conflict of interest (no)--Whether arbitrator's jurisdiction limited to defects identified by Engineer (no)--Whether arbitrator has jurisdiction over all matters referred to Engineer (yes)--Arbitration Act 1996, s 67 Engineer's decision valid precondition to arbitration despite conflict of interest and failure to apply rules of natural justice The Secretary of State entered into a contract with Amec Civil Engineering Ltd for renovation works at Thelwall Viaduct. The contract was on the ICE conditions (5th edn). The works were substantially completed in 1996. Defects came to light in 2002. The Highways Agency referred the matter to the Engineer under the contract, but also made a parallel claim against the Engineer. Amec's correspondence was not made available to the Engineer, nor was Amec afforded an opportunity to make submissions. The decision was requested urgently and the Engineer drafted it before receiving the formal request which was not copied to Amec. The

Journal

Arbitration Law Reports and ReviewOxford University Press

Published: Jan 1, 2004

There are no references for this article.